Appealing a tree decision in Australia: what the ACT, Victoria, New South Wales and Queensland set out
Four Australian systems say who hears an appeal against a tree decision: in the ACT, internal review and then its tribunal; in Victoria, VCAT; in New South Wales, the Land and Environment Court; in Queensland, the Planning and Environment Court or a tribunal.
Checked against the sources at the bottom of this page on October 10, 2026. Rules, fees and pay change: the source has the last word.
This page reports what the official source says. It is not legal advice: ask the office named here. The ACT rules come from the Urban Forest Act 2023 of the Australian Capital Territory (ACT), republication 4 effective January 2, 2026. Victoria's come from the Planning and Environment Act 1987, version 167 effective August 3, 2026, with the Victorian Civil and Administrative Tribunal (VCAT) planning page and the Wellington planning scheme's Vegetation Protection Overlay clause. New South Wales is covered through the Land and Environment Court pages, and Queensland through the Planning Act 2016. It covers the ACT, Victoria, New South Wales and Queensland only. Councils' permit rules are covered in the guide to tree rules in Australian and New Zealand councils.
The four systems side by side
| Place | First step the source names | Tribunal step |
|---|---|---|
| ACT | For approvals, cancelled approvals and tree management plans, an application to the decision-maker for internal review, within 14 working days of the internal review notice | The ACT Civil and Administrative Tribunal (ACAT), for the decisions the Act lists, including the result of an internal review |
| Victoria | None named in the Act: an applicant goes straight to the Tribunal | VCAT, for a refused permit, a failure to decide, a permit condition, and an objector's challenge to a grant |
| New South Wales | The court page counts time from the determination or from a review of it; the appeal goes to the Land and Environment Court | The Land and Environment Court, Class 1, usually within 6 months of notice of the determination or of a deemed refusal; objector appeals within 28 days |
| Queensland | None named in the Planning Act 2016 | The Planning and Environment Court or, for some matters, a tribunal; 20 business days for most appeals under section 229(3)(h) |
The ACT
Part 8 of the Urban Forest Act 2023 splits decisions into two lists in its Schedule 1. Part 1.1 lists decisions that can be reviewed internally first. They include approving or refusing an activity under section 28, cancelling an approval under section 31, approving or refusing a tree management plan under section 85, and several canopy contribution decisions. Part 1.2 lists decisions that go straight to ACAT, among them a tree protection direction under section 44, the registration of a tree under sections 55, 60 and 66, and a site declaration under section 69.
For an internal review, section 133 says the application is in writing with the applicant's name, address and reasons, and that making it automatically stays the decision until it is dealt with. Under section 134 the conservator may ask the advisory panel for advice, which the panel gives within 30 working days. The decision-maker then reviews the decision and confirms, varies or sets it aside within 35 working days of the day it receives the advice or the application. Section 136 and item 7 of Part 1.2 let the entity named in the schedule apply to ACAT for review of that internal review decision.
Victoria
In the Wellington planning scheme a tree rule sits in a Vegetation Protection Overlay, and a review follows the ordinary planning permit route set out in the Act. Clause 42.02-2 says a permit is required to remove, destroy or lop any vegetation specified in a schedule to the Vegetation Protection Overlay, unless the table at clause 42.02-3 says a permit is not required.
Section 77 of the Planning and Environment Act 1987 says an applicant for a permit may apply to the Tribunal for review of a decision by the responsible authority to refuse the permit. Section 79 covers a failure to grant a permit within the prescribed time, and section 80 covers any condition in a permit. Section 82 lets an objector apply for review of a decision to grant a permit. A planning scheme may exempt classes of application from that right. The VCAT planning page lists the cases it hears, including review of a responsible authority's permit decision. It says VCAT cannot help with fencing or tree disputes between neighbours and points to the Dispute Settlement Centre of Victoria for those. Neither that VCAT page nor sections 77 to 82 state a time limit for applying.
New South Wales
The Land and Environment Court says Class 1 proceedings are merits review of administrative decisions of local or State government. In hearing the appeal the court sits in the place of the original decision-maker and re-exercises its decision-making functions, and its decision is final and binding and becomes that of the original decision-maker. The court's development appeals page describes appeals under section 8.7 of the Environmental Planning and Assessment Act 1979 against a consent authority's determination of a development application. Such an appeal is usually made within 6 months after the applicant received notice of the determination, or after the day the application is taken to have been refused. A deemed refusal arises after 40 days for ordinary development, 60 days for designated or integrated development and 90 days for State significant development. Objector appeals under section 8.8 are made within 28 days after notice of the determination was given. The miscellaneous appeals page lists appeals under the Native Vegetation Act 2007, including stop work orders and directions for remedial work, among the matters the court hears. The court pages treat tree and hedge disputes between neighbours as a separate Class 2 matter, which this page does not cover.
Queensland
Section 229 of the Planning Act 2016 says Schedule 1 states which matters may be appealed to the Planning and Environment Court or a tribunal, and who may appeal. An appellant may start an appeal within the appeal period. For an appeal against a deemed refusal the appeal period is any time after the deemed refusal. For most other appeals the period is 20 business days after notice of the decision, including an enforcement notice, is given to the person. A note points to the Planning and Environment Court Act for the court's power to extend it. Schedule 1 lets an applicant appeal the refusal of all or part of a development application, a deemed refusal, a provision of the approval, or the decision to give a preliminary approval. The Act names clearing of vegetation in its transitional sections and refers to the Vegetation Management Act 1999, but the appeal sections do not name tree decisions. Schedule 1 does name appeals to the Planning and Environment Court against a local government decision under a local law about the use of premises or the erection of a building or other structure. No council tree local law was read for this page.
Sources
- ACT Parliamentary Counsel, Urban Forest Act 2023 (A2023-14), republication 4 effective January 2, 2026, read October 9, 2026
- Victorian Chief Parliamentary Counsel, Planning and Environment Act 1987, version 167 effective August 3, 2026, read October 9, 2026
- Victorian Civil and Administrative Tribunal, Before you apply: planning disputes, read October 9, 2026
- Victorian Planning Provisions, Wellington Planning Scheme clause 42.02 Vegetation Protection Overlay (clause 42.02-2 as amended by VC224 on October 28, 2022), read October 9, 2026
- Land and Environment Court of New South Wales, Class 1: Environmental planning and protection appeals, read October 10, 2026
- Land and Environment Court of New South Wales, Development appeals, read October 10, 2026
- Land and Environment Court of New South Wales, Miscellaneous appeals, read October 10, 2026
- Queensland Parliamentary Counsel, Planning Act 2016, section 229 and Schedule 1, read October 10, 2026