ArbNation Join free

Arboricultural Association Safety Guide 1, Tree Climbing and Aerial Rescue: the checklist

Safety Guide 1 is a seven-page UK checklist of 15 sections and 73 questions for tree climbing and aerial rescue, drawn from Technical Guide 1 and tied to the Industry Code of Practice.

Checked against the sources at the bottom of this page on October 19, 2026. Rules, fees and pay change: the source has the last word.

The named training bodies and codes are described here as published. It is not training and does not teach the work.

What the leaflet is

The Arboricultural Association (AA) lists five Safety Guides. It built them to help operators, and the Competent Person who supervises them, find the key safety points in tree work at height. Each Safety Guide comes from the Technical Guide of the same title. Safety Guide 1, dated December 2020, derives from Technical Guide 1: Tree Climbing and Aerial Rescue.

The leaflet states that it is not a substitute for adequate training or for the full Technical Guide. Its notes on good practice are not compulsory. It assumes the decision to climb has already been made. For that decision it points to the Industry Code of Practice for Arboriculture: Tree Work at Height (ICoP). The leaflet adds that climbing should only be undertaken when it is not reasonably practicable to work from ground level or from a platform, in that order. The ICoP's key principles apply when the leaflet is used.

The AA page adds that the Safety Guides can be used to monitor activities on site and as a record of auditing and actions required. The same ICoP lists Technical Guide 1 as the technical guidance for climbing and aerial rescue.

The key principles in section 1

Section 1.5 sets out five principles. All work at height is planned, organised, supervised and managed. Lifting and lowering systems are properly designed, with compatible components. Equipment is suited to the task and subject to periodic inspection and examination. Maintenance keeps equipment safe for use. Everyone in a climbing operation has the training and experience for their tasks.

The 15 checklist sections

Sections 2 to 16 are checklists with Yes, No and N/A columns. A notes page follows with fields for the date, location, observer, the person observed, comments, actions and the date actions were completed.

Sections of Safety Guide 1
SectionNo.Subjects
2 Planning and management11Whether climbing is the most appropriate method, a recorded site-specific risk assessment, enough personnel including for rescue, weather, enough time
3 Roles and responsibilities4Proficiency, supervision, agreed communication between climbers and ground staff
4 On-site preparation7Tree condition assessment, drop and working zones, entry procedures, PPE
5 Occupational health4Fitness, situational awareness, muscular-skeletal disorders and fatigue
6 Personal fall protection systems4Primary system and backup, connection points on the harness
7 A strategy for access3Method chosen from the tree assessment and climbers' abilities, team familiarity with rescue techniques
8 Selecting an ascent technique7Fall distance, anchoring, full-body-weight tests of new anchors where practical, descending when spikes are used
9 Managing slack and positioning5Potential fall distance not above 500 mm, two high anchors where practical, adjustable lanyard, pendulum swing
10 Descent5Uninterrupted descent, rope length, termination of systems, controlled descent
11 Anchors and anchor point selection5Training in selection, foreseeable loading, load and body-weight tests
12 Equipment: general2Suitability for the task, PPE in good condition
13 Building a system4Conformity standard, configuration to the maker's guidance, compatible components
14 Equipment for access and rescue2Components used to the maker's guidance and technical guidance
15 Inspection, care, storage and maintenance4Training, product lifespan, records of issue, inspection, withdrawal and disposal, pre-use checks
16 Aerial rescue6Rescue plan, resources immediately available, trained rescuers, practice at regular intervals, removing the casualty without risk to the rescuer

How it relates to other UK sources

The ICoP asks for an effective, documented and well-communicated rescue plan, and section 16 of the leaflet turns that into six questions. The ICoP also sets a minimum of two people during all tree work at height, with at least one equipped to perform aerial rescue without delay. The HSE aerial work page says the same. The leaflet's further reading lists the ICoP (second edition, May 2020), Technical Guides 1 to 5, and FISA 802 on emergency planning and FISA 805 on training and certification.

The leaflet also points to the Health and Safety Executive tree work pages and to the Forest Industry Safety Accord for forestry safety information.

Sources