Before clearing land in the US: the EPA stormwater permit and state equivalents
The EPA's construction stormwater rules apply once a job disturbs one acre of land, or less if it is part of a larger plan. Most states run their own version, and Texas sets its own acre bands.
Checked against the sources at the bottom of this page on October 16, 2026. Rules, fees and pay change: the source has the last word.
This page reports what the official source says. It is not legal advice: ask the office named here. The federal text comes from the EPA's pages on construction stormwater, the 2022 Construction General Permit (CGP) and the NPDES stormwater program. The state example is the Texas Commission on Environmental Quality (TCEQ). The Clean Water Act section 404 text is on the EPA's overview page.
The one-acre trigger
The EPA says a Clean Water Act permit is required for stormwater discharges from any construction activity that disturbs:
- 1 acre or more of land, or
- less than 1 acre, but as part of a common plan of development or sale that will end up disturbing 1 or more acres.
The EPA defines construction activity to include earth-disturbing work such as clearing, grading and excavating, plus other construction-related activities that could generate pollutants. Clearing is named in that definition.
Why the EPA regulates it
On the EPA's account, rain washes over loose soil and materials stored outside. The runoff can pick up sediment, debris and chemicals and carry them to storm sewers, rivers, lakes or coastal waters. The EPA lists sediment, solid and sanitary wastes, phosphorus, nitrogen, pesticides, oil and grease, concrete truck washout, construction chemicals and construction debris as the pollutants commonly associated with construction sites.
The federal minimum rules
Every NPDES permit for construction stormwater must address the federal effluent limitation guidelines for construction and development, called the C&D rule. The rule is at 40 CFR 450.21. The EPA summarizes its minimum limits:
- design, install and maintain effective erosion and sediment controls and pollution prevention measures to minimize discharge of pollutants;
- stabilize disturbed areas immediately when construction has ceased and will not resume for more than 14 days;
- prohibit dewatering discharges unless managed by appropriate controls;
- prohibit discharge of concrete washout wastewater (unless managed by appropriate control) and of washout or cleanout of stucco, paint, form release oils and other wastewater materials;
- prohibit discharge of fuels, oils or other pollutants used for vehicles, and of soaps or solvents used to wash vehicles and equipment.
The EPA's general permit and where it applies
The EPA's Construction General Permit covers stormwater discharges from construction in areas where the EPA is the NPDES permitting authority. That is EPA Regions 1 to 10 in the areas it administers. The 2022 CGP expires on February 16, 2027. The EPA published a notice on August 3, 2026 that it seeks comment on a proposed 2027 CGP, and public comment ran to September 17, 2026 after an extension. The 2022 CGP has appendices for definitions, areas of coverage, waivers, endangered species, historic property screening, buffer requirements, a Notice of Intent form and a Notice of Termination form.
The EPA's NPDES stormwater program page names three sources it regulates: municipal storm sewers, construction activities and industrial activities. It says operators of these sources might be required to obtain an NPDES permit before they discharge stormwater. Most states are authorized to run the stormwater permitting program. The EPA remains the permitting authority in a few states, in territories and on most land in Indian Country.
A state example: Texas
TCEQ issued the renewed Construction General Permit, TXR150000, effective March 5, 2023. The permit expires on March 5, 2028, and TCEQ held a stakeholder meeting on its renewal on June 9, 2026. TCEQ regulates construction activities under it if they discharge stormwater to any surface water in the state and disturb an acre or more of soil. It sorts them by size:
| Soil disturbed | TCEQ category |
|---|---|
| 5 acres or more, or part of a larger plan that will disturb 5 or more | Large construction activity, regulated under the permit |
| At least 1 but less than 5 acres, or part of a larger plan in that range | Small construction activity, regulated under the permit |
| Less than 1 acre and not part of a larger plan reaching 1 acre | Not regulated by this general permit |
The permit requires construction site operators to develop and implement a Stormwater Pollution Prevention Plan (SWP3) before construction begins. TCEQ lists two waivers for small construction activities, one for periods of low potential for erosion and one based on low rainfall erosivity. It also names a separate TCEQ route for clearing of acreage in the Edwards Aquifer recharge and contributing zones, handled by its regional offices.
Section 404 and fill in waters
Clean Water Act section 404, as the EPA prints it, lets the Secretary of the Army issue permits for the discharge of dredged or fill material into navigable waters at specified disposal sites. Subsection (f)(1) lists discharges that are not prohibited under the section. They include discharges from normal farming, silviculture and ranching activities, such as harvesting for the production of food, fiber and forest products. They also include construction or maintenance of farm roads or forest roads built and maintained under best management practices. Subsection (f)(2) says a discharge incidental to bringing an area of the navigable waters into a use it did not have before, where flow or circulation may be impaired or the reach of the waters reduced, requires a permit.
The two permits cover different things. Stormwater concerns runoff from disturbed soil. Section 404 concerns dredged or fill material placed in waters. For land clearing bids, see the guide to public tree bids and land clearing contracts.
Sources
- US EPA, Stormwater Discharges from Construction Activities, last updated August 10, 2026, read October 16, 2026
- US EPA, 2022 Construction General Permit (CGP), last updated August 3, 2026, read October 16, 2026
- US EPA, NPDES Stormwater Program, last updated May 4, 2026, read October 16, 2026
- Texas Commission on Environmental Quality, Stormwater General Permit for Construction Activities (TXR150000), read October 16, 2026
- US EPA, Overview of Clean Water Act Section 404, read October 16, 2026