ArbNation Join free

Buying a used crane or loader crane: the paperwork and official lookups to ask for

HSE wants the last thorough-examination record to travel with used lifting equipment, on a 6 or 12-month cycle. OSHA's crane standard fixes an annual inspection with a signed record kept 12 months.

Checked against the sources at the bottom of this page on October 15, 2026. Rules, fees and pay change: the source has the last word.

This page reports what the official source says. It is not legal advice: ask the office named here. Climbing and rigging gear has its own list in the guide to buying used gear.

Great Britain: the examination record

HSE puts a duty on anyone who supplies second-hand equipment for use at work, including one-off sales by users. Where periodic inspection or thorough examination is required, as for lifting equipment, copies of the last record should also be provided. HSE adds that "sold as seen" cannot be used to avoid the duty.

HSE's page on lifting equipment describes a thorough examination as a systematic and detailed check of the equipment and its safety-critical parts. A competent person carries it out at set intervals and then completes a written report. Examination and inspection records should be producible when lifting equipment leaves the business, including by second-hand sale.

EquipmentInterval between thorough examinations
Lifting equipment and accessories used to lift people6 months
All lifting accessories6 months
All other lifting equipment12 months

These intervals apply unless an examination scheme drawn up by a competent person sets others. The report carries the information in Schedule 1 of the Lifting Operations and Lifting Equipment Regulations 1998, known as LOLER. That includes the examination date, the date the next one is due and any defect that is or could become a danger to people. HSE says there is no longer a defined form, provided all 11 items in the Schedule appear.

A first-use examination is needed unless the equipment has a Declaration of Conformity less than one year old and was not assembled on site. Further examinations follow exceptional circumstances: damage or failure, long periods out of use, or major changes such as modifications or replacement of critical parts. HSE keeps the retention periods in Table 3 of its thorough examination publication.

United States: 29 CFR 1926.1412

The OSHA standard for cranes and derricks in construction, Subpart CC, sets the crane inspections and their records. The employer who carries out an inspection documents it.

InspectionWho and whenRecord
Each shiftA competent person begins a visual inspection before each shiftNone named
MonthlyEach month in service, the same checks as the shift inspectionItems checked and results; name, signature and date of the inspector; kept at least 3 months
AnnualA qualified person at least every 12 months, with disassembly as necessaryItems checked and results; name, signature and date of the inspector; kept at least 12 months
After modification or additionA qualified person, before initial use, including functional testingNone named
After repair or adjustmentA qualified person, before initial useNone named
Idle 3 months or moreA qualified person, to the monthly standard, before initial useNone named

The annual inspection list covers structure including the boom and jib, welds, fasteners, sheaves and drums, brakes and clutches, safety devices and operational aids, the power plant, tires, hydraulic hoses and pumps, and functional testing of the equipment as configured.

The modification rule ties the work to the approval obtained under section 1926.1434 on equipment modifications. For repairs, the qualified person decides whether the repair meets the manufacturer's criteria, and if none exist, whether a registered professional engineer must develop them.

Severe service gets its own paragraph. Where loading that may have exceeded rated capacity, shock loading or prolonged exposure to a corrosive atmosphere makes damage or excessive wear reasonably probable, the employer stops using the equipment and a qualified person inspects it for structural damage. The standard also requires any part of the manufacturer's inspection procedures that goes further or runs more often than the standard to be followed.

New Zealand: second-hand plant

WorkSafe New Zealand's good practice guide on safe use of machinery says the duties of suppliers do not apply to second-hand plant sold "as is". A business that buys it still has a duty not to create risks for its workers. The guide lists what a buyer should look at: the machine's history and previous use, whether it is at the end of its life, its specifications and maintenance information, and the guarding. It also lists a check by a certified engineer.

For imported machinery, the guide names AS/NZS 4024 as the New Zealand benchmark. A CE marking alone does not mean a machine meets New Zealand's requirements under the Health and Safety at Work Act.

Sources