CDM 2015 and tree work on building sites in the UK

The Construction (Design and Management) Regulations 2015 give duties to clients, principal designers, principal contractors and contractors. A project is notifiable above 30 working days with more than 20 workers, or above 500 person days.

Checked against the sources at the bottom of this page on October 19, 2026. Rules, fees and pay change: the source has the last word.

This page reports what the official source says. It is not legal advice: ask the office named here. The text below follows the Health and Safety Executive (HSE) pages on CDM 2015 dutyholders and the regulations themselves, Statutory Instrument 2015 No. 51.

Who holds a duty

The regulations name five dutyholders on a project: the client, the principal designer, the principal contractor, designers and contractors. Part 2 of the instrument holds the client duties. Part 3 holds the health and safety duties and roles of everyone else. Part 4 sets general requirements for all construction sites, from safe places of work to traffic routes, excavations and lighting.

HSE defines a contractor as anyone who directly employs or engages construction workers or manages construction work. That takes in sub-contractors and any self-employed worker or business that carries out, manages or controls the work. The instrument says the same in regulation 2: a contractor is any person who, in the course or furtherance of a business, carries out, manages or controls construction work.

What counts as construction work

Regulation 2 defines construction work as the carrying out of any building, civil engineering or engineering construction work. The list that follows covers the construction, alteration, repair, maintenance and demolition of a structure. It also covers the preparation for an intended structure, which includes site clearance, exploration, investigation and excavation, and the clearance or preparation of the site or structure for use or occupation at its conclusion.

Neither the HSE pages nor the instrument mention trees by name. The definition lists site clearance, and the wording above is all the sources print on the point.

Client duties and domestic clients

A client is any person for whom a project is carried out. A domestic client is one for whom the project is not carried out in the course or furtherance of a business of that client. Regulation 7 deals with domestic clients, and HSE keeps separate pages for commercial and domestic clients.

HSE describes how the client duties move on a domestic project. A contractor who is the only contractor takes on the client duties along with their own contractor duties. HSE adds that this should involve no more than the contractor normally does to comply with health and safety law.

Where a domestic project has more than one contractor, the principal contractor normally takes on the client duties, and the other contractors treat the principal contractor as the client. If the domestic client appoints no principal contractor, the role falls to the contractor in control of the construction phase. A domestic client can instead ask the principal designer to take on the client duties, but HSE says that must be confirmed in a written agreement.

Principal contractor

HSE says a principal contractor is appointed by the client to control the construction phase of any project involving more than one contractor. The principal contractor must have the skills, knowledge, experience and, where relevant, the organisational capability for the role. The HSE list of duties runs as follows.

  • Plan, manage, monitor and coordinate the entire construction phase.
  • Take account of the risks to everyone affected, including members of the public.
  • Liaise with the client and principal designer for the length of the project.
  • Prepare a written construction phase plan before the construction phase begins, then implement, review and revise it.
  • Keep arrangements in place for managing health and safety through the construction phase.
  • Consult and engage with workers about their health, safety and welfare.
  • Provide suitable welfare facilities from the start and maintain them.
  • Check that anyone they appoint has the skills, knowledge, experience and, where relevant, organisational capability.
  • Give all workers site-specific inductions and any further information and training they need.
  • Take steps to prevent unauthorised access to the site.
  • Share information with the principal designer for the pre-construction phase.

Contractors, and where an arborist sits

HSE does not place arborists in the contractor role by name. The duties it sets for contractors are in the table below.

Contractor duties on the HSE page
SituationDuties HSE lists
Every projectMake the client aware of the client duties before any work starts. Plan, manage and monitor the work of the contractor and its workers, with the risks to the public in mind. Check that workers have the skills, knowledge, training and experience, or are obtaining them. Give a suitable site-specific induction, unless the principal contractor already has. Provide supervision, information and instructions. Start work only once reasonable steps have been taken to prevent unauthorised access. Provide suitable welfare facilities from the start and maintain them.
More than one contractorCoordinate the work with others in the project team. Comply with directions given by the principal designer or principal contractor. Comply with the parts of the construction phase plan that apply to the work.
Only contractorA construction phase plan is drawn up before the site is set up.
Only contractor, domestic clientTake on the client duties along with the contractor duties.

Notification

Regulation 6 makes a project notifiable in two cases. One is work scheduled to last longer than 30 working days with more than 20 workers on site at the same time at any point. The other is work scheduled to exceed 500 person days. The client must then give notice in writing to the Executive as soon as is practicable before the construction phase begins. The notice carries the particulars in Schedule 1 and is displayed in the site office where any worker can read it. It is updated when needed. HSE keeps the F10 notification form for this.

Schedule 1 lists 15 particulars. They include the site address, the local authority and a brief description of the project. They also cover contact details for the client, principal designer and principal contractor, the planned start date and duration, the most people expected at work and the planned number of contractors.

Construction phase plan and welfare

Regulation 12 is the construction phase plan and the health and safety file. HSE lists a construction phase plan guide as CIS80. Schedule 2 sets the minimum welfare facilities for construction sites: sanitary conveniences, washing facilities, drinking water, changing rooms and lockers, and facilities for rest. Schedule 3 lists work involving particular risks, which starts with work that puts workers at risk of burial under earthfalls.