Deposits and progress payments: the California and Massachusetts limits on contractor deposits

California caps a home improvement down payment at the lesser of US$1,000 or 10 percent of the contract price. Massachusetts caps a deposit at the greater of one-third of the price or the cost of special-order materials.

Checked against the sources at the bottom of this page on October 16, 2026. Rules, fees and pay change: the source has the last word.

This page reports what the official source says. It is not legal advice: ask the office named here.

At a glance

StateDeposit limitWritten contract from
CaliforniaThe lesser of US$1,000 or 10 percent of the contract priceMore than US$500
MassachusettsThe greater of one-third of the total price or the cost of special-order or custom-made materialsMore than US$1,000

California

The Contractors State License Board (CSLB) says the down payment for a home improvement job or swimming pool cannot be more than the lesser of US$1,000 or 10 percent of the contract price, excluding finance charges. The CSLB adds that there are no exceptions for special-order materials. In California a written contract is required for all home improvement projects over US$500, and changes to the contract must also be in writing.

Business and Professions Code section 7159 is the statute. It requires a contract that charges a down payment to carry a heading "Downpayment" and a space for the actual amount. It also requires a statement in at least 12-point boldface type that the downpayment may not exceed the lesser of US$1,000 or 10 percent of the contract price. A contract with progress payments before completion must carry a schedule headed "Schedule of Progress Payments." Each payment is stated in dollars and cents and tied to the work or services and the materials and equipment supplied.

The boldface progress-payment statement in section 7159 reads in part that it is against the law for a contractor to collect payment for work not yet completed or materials not yet delivered. It adds that a contractor may require a downpayment. The CSLB says payments to the contractor cannot exceed the value of the work performed, apart from the down payment. It also says a detailed written payment schedule must be in the contract.

Massachusetts

Chapter 142A, section 2 of the Massachusetts General Laws covers agreements to perform residential contracting services in an amount over US$1,000. Each must be in writing and include a time schedule of payments, with the amount of each payment stated in dollars, including all finance charges. The agreement must also give the contractor's registration number, the start date and the scheduled completion date.

The section limits deposits. A deposit required before work starts shall not exceed the greater of two figures. One is one-third of the total contract price. The other is the actual cost of special-order or custom-made materials or equipment that must be ordered before work begins. No final payment shall be demanded until the contract is completed to the satisfaction of the parties. A contract may not contain an acceleration clause that lets the holder declare the balance due because it deems itself insecure. The contractor may instead require that funds in the owner's possession go into a joint escrow account.

The section also says contracts that fail its requirements are not invalid solely because of the noncompliance. It requires a clear notice, in ten-point bold type or larger above the signature space, reading "Do not sign this contract if there are any blank spaces."