Environmental Permit exemptions for chipping and storing tree waste in England (T6, U1)
The Environment Agency's T6 exemption covers chipping and shredding waste wood and plant matter, with up to 500 tonnes treated or stored over any 7 days. Virgin wood from tree work is not classed as waste.
Checked against the sources at the bottom of this page on October 19, 2026. Rules, fees and pay change: the source has the last word.
This page reports what the official source says. It is not legal advice: ask the office named here. The wording below comes from the Environment Agency's GOV.UK guidance on the T6 and U1 waste exemptions and on registering exemptions, plus Schedule 2 of the Environmental Permitting (England and Wales) Regulations 2016. The GOV.UK pages apply to England.
What an exempt waste operation is
Schedule 2 of the 2016 Regulations is headed Exempt facilities: general. Paragraph 4 sets the requirements for an exempt waste operation. The operation must fall within a description in Part 1 of Schedule 3 and meet that description's general and specific conditions. The operation and the business or undertaking running it must be registered. The type and quantity of waste, and the method of recovery or disposal, must be consistent with the objectives in Article 13 of the Waste Framework Directive.
The general condition in paragraph 3 is that the operation is not one that falls within Chapter 5 of Part 2 of Schedule 1, the waste management chapter. The descriptions run under the codes U1 to U16, T1 to T33, D1 to D8 and S1 to S3. The appropriate agency is the registration authority for waste operations in Part 1 of Schedule 3. For T3 and T7 it is the local authority.
T6: treating waste wood and plant matter
The Environment Agency guidance, first published April 28, 2014 and last updated July 21, 2025, says the T6 exemption allows chipping, shredding, pulverising or cutting of waste wood and plant matter to make it suitable for a specific purpose. The products it names are mulch, panel board, fuel and surfacing for tracks and paths. Waste treated under T6 must suit its intended purpose. In its example, chemically treated wood cannot be shredded to make animal bedding or compost.
Where virgin wood stands
The guidance defines virgin wood as trees and branches resulting from forestry work or from management of land, gardens and parks. Virgin wood is not classed as waste. A T6 is not needed to chip, shred, pulverise or cut it. A T6 is also not needed for shredding twigs and leaves associated with tree surgery, or for clearing ground cover such as brambles. That holds where the material is left there to benefit the ecosystem or shredded for transporting elsewhere. The July 21, 2025 update added this wording. A December 21, 2015 update had already clarified that no T6 needs registering for tree and forestry maintenance work where the wood is cut, chipped or shredded and then left on the ground or taken off site for use elsewhere.
Where a T6 is needed
The guidance lists these activities as needing a T6 exemption.
- Chipping untreated waste wood, for example for fuel in a boiler.
- Cutting waste wood to a suitable size, for example for manufacture into chipboard.
- Bringing in waste wood and waste plant matter from another site.
- Treating chemically treated waste wood that will be used as fuel in specialised incineration or for panel board manufacturing.
Chemically treated waste wood is wood that has been preserved, varnished, coated, painted or exposed to chemicals. The guidance also lists what T6 cannot do. It cannot sort waste wood or plant tissue from other types of waste. It cannot treat wood sorted from mixed sources at a waste treatment facility. It cannot treat waste meant for landfill or incineration, except at a permitted R1-accredited incinerator. It cannot treat wood that is hazardous waste because of chemical treatment.
Waste codes, amounts and storage
| Item | What the page prints |
|---|---|
| Waste codes allowed | 02 01 03 and 20 02 01 (plant tissue waste); 03 01 01, 03 03 01 and 17 02 01 (wood); 15 01 03 (wooden packaging only) |
| Maximum amount | Up to 500 tonnes treated or stored over any 7-day period |
| Storage after treatment | Up to 3 months after chipping, shredding, pulverising or cutting |
| Registration | With the Environment Agency through the waste exemption service. Charities register by phone and pay nothing |
| Charging | Band 1 compliance charge, plus a registration charge for one or more exemptions at a time |
| Registration rules | No more than one of the same exemption at a site at one time. No registering an exemption already registered at the site by another business. No renewing more than one month before the 3-year registration period ends |
An environmental permit or a different exemption is required to treat or store waste that is not listed in T6, or more waste than the exemption allows. Related exemptions can use chipped, shredded, pulverised or cut waste wood: U1, U4 (burning waste as fuel in a small appliance), U8, U9, U12 (using mulch) and U13 (spreading plant matter to control weeds or add nutrients to soil).
U1: using waste in construction
The U1 guidance, last updated September 10, 2026, describes the exemption as one for farmers, builders, engineers and other businesses to use suitable waste for construction projects and maintenance work. It is valid for 3 years from registration and sits in charging band 1. Wood appears in two of its activities, and in both the waste must have been processed into chip form.
| Activity | Limit | Wood codes listed |
|---|---|---|
| Building tracks, paths, bridleways or car parks | Up to 1,000 tonnes over the 3-year registration period | 02 01 03, 03 01 01, 03 03 01, 03 01 05, 17 02 01, 19 12 07, 20 01 38 |
| Maintaining tracks, paths, bridleways or car parks | Up to 100 tonnes per linear mile, per year | 02 01 03 (plant tissue waste) and 03 01 01 (waste bark, cork and wood only) |
The guidance says U1 cannot be used for landscaping, land levelling or land reclamation as standalone activities. It cannot be used to treat waste to make it suitable for the purpose, and waste cannot be stored for more than 12 months before use. The waste used must match the codes for the activity, stay within the amount allowed, suit the construction activity and satisfy engineering standards. It must not be contaminated by pollutants such as plastic, asbestos fragments or oils and fuels. Flood risk permits and planning permission are named as other rules that may apply.
Registering
The Environment Agency's register-your-waste-exemptions page, last updated February 26, 2026, says registration is online and each exemption is valid for 3 years. It lists what a registrant needs: the exemptions wanted, business name, address and contact details, a Companies House number if there is one, and the address or grid reference of the site. Payment is by credit or debit card or bank transfer. Registration and exemptions are free for a charity working exclusively for a charitable purpose. VAT does not apply to any waste exemption.
Schedule 2 of the Regulations sets the same period. Paragraph 15 makes a first registration valid for 3 years and allows renewal at any time in the month before it becomes invalid. Paragraph 16 requires a registered business to tell the registration authority without delay of any change to its particulars, and allows the authority to remove the entry if it does not.
Routes along a road, river, track or other linear network have their own online form. The U1 page asks for grid references for the start and end of the area of activity, or maps showing all areas.
Sources
- Environment Agency, T6: treating waste wood and plant matter, GOV.UK guidance, last updated July 21, 2025, read October 19, 2026
- Environment Agency, U1: using waste in construction, GOV.UK guidance, last updated September 10, 2026, read October 19, 2026
- Environment Agency, Register your waste exemptions, GOV.UK guidance, last updated February 26, 2026, read October 19, 2026
- legislation.gov.uk, The Environmental Permitting (England and Wales) Regulations 2016, SI 2016/1154, Schedule 2, read October 19, 2026