FEMA Public Assistance rules for debris contractors: procurement under 2 CFR 200 and time-and-materials limits

Local governments paid with federal disaster money must follow 2 CFR 200.318 to 200.327 when they hire. The rules bar cost-plus-percentage-of-cost contracts and allow time-and-materials only with a ceiling price.

Checked against the sources at the bottom of this page on October 19, 2026. Rules, fees and pay change: the source has the last word.

This page reports what the official source says. It is not legal advice: ask the office named here. FEMA's procurement under grants page and the Code of Federal Regulations set the buying rules for a local government that uses federal disaster funds. Debris monitors and load tickets are covered in the guide to debris monitoring for contractors.

Which rules apply to which buyer

FEMA's procurement page says the federal standards apply differently depending on the type of entity, the cost, the contract type and amount, and the procurement method. Local governments and nonprofits follow 2 CFR 200.318 through 200.327. Where state, tribal, local and federal rules differ, the page points to the stricter one.

FEMA frames the exigency exception to competitive requirements around one point: communities must often act quickly to protect life, public health or safety, and property when a disaster strikes. The limits on cost-plus and time-and-materials contracts sit in the regulation.

General procurement standards in 200.318

2 CFR 200.318, paragraphs that reach a debris contract
ParagraphWhat it requires of the recipient or subrecipient
(a) Documented proceduresWritten procurement procedures that are consistent with state, local and tribal law and with sections 200.317 through 200.327
(b) OversightOversight to confirm contractors perform under the terms, conditions and specifications of their contracts or purchase orders
(c) Conflicts of interestWritten standards of conduct. No employee, officer, agent or board member with a real or apparent conflict may take part in selecting, awarding or administering the contract
(h) Responsible contractorsAwards only to contractors able to perform. The buyer considers integrity, public policy compliance, proper classification of employees, past performance, and financial and technical resources
(i) Procurement recordsRecords of each procurement, including the rationale for the method, the contract type, the selection or rejection of contractors, and the basis for the price
(j) Time-and-materials contractsAllowed only after a determination that no other contract is suitable, and only with a ceiling price that the contractor exceeds at its own risk

Time-and-materials contracts

Section 200.318(j) defines the contract. Its cost to the buyer is the actual cost of materials plus direct labor hours charged at fixed hourly rates that reflect wages, general and administrative expenses, and profit. The regulation explains that this formula gives an open-ended price and no profit incentive for cost control or labor efficiency.

For that reason each such contract must set a ceiling price that the contractor exceeds at its own risk. The buyer must also assert a high degree of oversight to obtain reasonable assurance that the contractor uses efficient methods and effective cost controls.

Cost and price analysis in 200.324

Section 200.324(a) requires a cost or price analysis for every procurement transaction above the simplified acquisition threshold, including contract modifications. The method and degree depend on the facts. As a starting point, the buyer must make independent estimates before it receives bids or proposals.

Section 200.324(b) limits prices built on estimated costs. They are allowable only to the extent the costs incurred, or the cost estimates in negotiated prices, would be allowable under subpart E of the part.

Section 200.324(c) is short. The recipient or subrecipient must not use the "cost plus a percentage of cost" and "percentage of construction costs" methods of contracting.

What stays with the local government

Section 200.318(k) leaves source evaluation, protests, disputes and claims with the recipient or subrecipient. It also says the federal agency will not substitute its judgment for the buyer's unless the matter is primarily a federal concern.

Hazard-tree eligibility is a separate question, covered in the guide to FEMA debris removal and hazardous trees.

Sources