Climbing and rigging words, extended: 30 more terms from the UK, NSW and NZ codes

Thirty terms for climbing gear, rope systems and lifting crew roles, defined in the UK Industry Code of Practice for tree work at height and in the New South Wales and New Zealand codes.

Checked against the sources at the bottom of this page on October 16, 2026. Rules, fees and pay change: the source has the last word.

The UK Industry Code of Practice for Arboriculture: Tree Work at Height, Edition 2 of May 2020, defines most of these terms. The rest come from WorkSafe New Zealand's approved code of practice for safety and health in arboriculture and from the SafeWork NSW tree work code. More climbing words are in the climbing glossary and the rigging glossary.

Gear and system words in the ICoP

TermMeaningSource
Anchor deviceA part, or a set of parts, that connects to an anchor or anchor point.UK ICoP Edition 2, Part 2, page 8
AssemblyA unit made of two or more connected components.UK ICoP Edition 2, Part 2, page 8
BackupA device, safety line or system that gives protection or support if the structure or the primary system fails. The ICoP's definition says this includes the main line, components or the anchor.UK ICoP Edition 2, Part 2, page 8
ComponentOne element of a system.UK ICoP Edition 2, Part 2, page 8
ConfigurationA collection of parts in which the relative organisation of the components is defined.UK ICoP Edition 2, Part 2, page 8
ConnectorA component that can be opened and closed, and can sit in a secure or locked position.UK ICoP Edition 2, Part 2, page 8
Descending devicesMechanisms for descending a rope, often with a smooth cam, a roller or another friction system that regulates the speed of descent. The ICoP adds that some have auto-locking functions and fail-to-safe mechanisms.UK ICoP Edition 2, Part 2, page 8
ElementA component part of a system.UK ICoP Edition 2, Part 2, page 8
HarnessAn assembly of elements worn by the user, giving points for connection to systems. It adjusts to fit and can support an operator in suspension through a ventral, sternal or dorsal attachment.UK ICoP Edition 2, Part 2, page 8
InspectionLooking closely at a process, system or piece of equipment.UK ICoP Edition 2, Part 2, page 9

Crew roles and planning words in the ICoP

TermMeaningSource
Appointed personA person with training, practical and theoretical knowledge and experience of lifting operations.UK ICoP Edition 2, Part 2, page 8
Approved code of practice (ACoP)A document of practical advice on how to comply with the law in Great Britain. The ICoP says it has a special legal status.UK ICoP Edition 2, Part 2, page 8
AssessorA person with the knowledge, ability, training and experience to make visual and cognitive judgements and decide on a suitable course of action.UK ICoP Edition 2, Part 2, page 8
Crane supervisorThe person who controls the lifting operation and sees that it follows the appointed person's safe system of work.UK ICoP Edition 2, Part 2, page 8
Method statementA written document that details how a task or operation will proceed under a safe system of work. The ICoP says it is used particularly where tasks or sites are safety-critical or complex.UK ICoP Edition 2, Part 2, page 9
ProficiencyThe combination and use of skills, knowledge and experience, trained and latent, to reach a wanted outcome consistently. The ICoP says it can be judged by the efficiency, quality and effectiveness of the outcome.UK ICoP Edition 2, Part 2, page 9
Proficient operatorA skilled, knowledgeable and experienced operator who can perform specific tasks.UK ICoP Edition 2, Part 2, page 9
Responsible personThe individual who carries the final legal responsibility for all activities under their control.UK ICoP Edition 2, Part 2, page 9
Risk assessmentAn assessment of the hazards and risks that belong to a particular task, operation, site or machine.UK ICoP Edition 2, Part 2, page 9
SignallerThe person who directs a crane operator so the crane and load move safely.UK ICoP Edition 2, Part 2, page 9
SlingerThe person who supervises the attachment and detachment of crane loads.UK ICoP Edition 2, Part 2, page 9

Words from the New Zealand and New South Wales codes

TermMeaningSource
AloftThe state of a climber once they have left the ground.NZ arboriculture code, definitions, page 11
Arborist climbing lineA rope used only to support a climber aloft. The New Zealand code sets its minimum breaking strength at 22 kN when new.NZ arboriculture code, definitions, page 11
Auto-locking carabinerA carabiner that moves into the locked position by itself on closing, and takes at least three distinct movements to open.NZ arboriculture code, definitions, page 11
ClimbingIn the New Zealand code, going up, going down or moving sideways in a tree while carrying out operations.NZ arboriculture code, definitions, page 11
Climbing sawAny chainsaw used while the operator is in the tree.NZ arboriculture code, definitions, page 11
SpragA point, burr or patch of roughness on a metal surface.NZ arboriculture code, definitions, page 13
New Zealand StandardA standard approved by the Standards Association of New Zealand, or in force at the time, and available from that body.NZ arboriculture code, definitions, page 13
Trainee arboristAn employee or student doing work who is not yet competent and is supervised by a competent person.NZ arboriculture code, definitions, page 13
DunnagePacking placed under and between a load to protect and support it in transport.SafeWork NSW tree work code, glossary, page 77

The ICoP also defines the safety factor, the working load limit and the minimum breaking strength, which are in the glossary of gear ratings and records.