Pre-climb checks and the tree-climbing plan: what WorkSafeBC, HSE and the ICoP list

WorkSafeBC is the only regulator here that sets out the contents of a written tree-climbing plan, in section 26.12.0.3. HSE, the ICoP, the NSW code and the New Zealand code list pre-climb checks without a plan form.

Checked against the sources at the bottom of this page on October 19, 2026. Rules, fees and pay change: the source has the last word.

The named codes and training bodies are described here as published. It is not training and does not teach the work.

Credits: SafeWork NSW text is adapted from the Tree works code of practice (March 2026), copyright State of New South Wales (SafeWork NSW), licensed under Creative Commons Attribution 4.0; changes were made, because the text is summarised and reworded. WorkSafe New Zealand material is summarised from its Approved Code of Practice for Safety and Health in Arboriculture (November 2012), with the source acknowledged. HSE text is adapted under the Open Government Licence v3.0.

WorkSafeBC: the plan and what comes before it

WorkSafeBC Part 26 sets the tree-climbing rules in sections 26.12.0.1 to 26.12.0.6. They apply to a workplace other than a forestry operation, and took effect on December 1, 2021.

Section 26.12.0.2 has the employer see that only a qualified arborist or trainee arborist climbs. Before the climb, a qualified arborist determines that each tree can withstand the loads of the climbing and of the ground work around it. A tree-climbing plan is prepared and communicated to each worker involved. A plan prepared by a trainee arborist is approved by a qualified arborist.

Section 26.12.0.3 lists what the plan holds. For each tree climbed or affected, the hazards and risks are visually assessed for tree structure, species failure patterns such as rot, the climbing itself, and the ground work. The plan then names how each hazard is eliminated or minimized, and identifies:

  • the tree-climbing system to be used;
  • the type and location of the initial anchor point;
  • the name and duties of each worker involved;
  • the protective equipment each worker uses;
  • the means of communication;
  • the emergency response, evacuation and rescue procedures, including for an arborist who cannot self-rescue.

The plan is documented, and a hazard found later is added by amendment and communicated before the change is used.

Section 26.12.0.6 adds an inspection of the climbing system by a qualified arborist before it is first used on each work shift. Equipment that arrests a fall comes out of service with the whole system.

The WorkSafeBC bulletin

Bulletin WS-2023-06, Keeping arborists safe during tree removal in residential and recreational settings, dates from November 2023. Its summary names four steps: identifying the risks, using control measures, developing a tree-climbing plan, and checking that workers are qualified. It says arborists face increased risk when the tree is in poor health, dead or decaying, or the work area is limited. The bulletin text opened does not list plan fields. Section 26.12.0.3 does.

HSE

The HSE tree climbing page says the Work at Height Regulations 2005 do not ban climbing. Employers have a duty to plan the work and select suitable equipment. Climbing with a personal fall protection system can be done only if three things hold. A risk assessment has shown the work can be done safely. Other equipment, such as a platform, is not justified. The user and enough available people have had task-specific training, including rescue.

Where possible the system should be attached to two load bearing anchor points. A work positioning system should have a backup unless that is not reasonably practicable. For more detail, HSE refers to the ICoP and to Technical Guide 1 on tree climbing and aerial rescue.

The ICoP

The ICoP's section 3.3.6 has a safe system of work in place before tree work at height starts, informed by a risk assessment. The competent person appraises the work, usually at the quotation stage, and drafts a site-specific risk assessment with emergency procedures. The proficient operator makes an on-site appraisal on the day and validates that assessment.

Section 3.4 calls for a site survey and assessment before work starts. Its parts include the survey area, the work required, the tree condition assessment, constraints, site conditions, electricity and underground services. Section 3.5.1 says work at height should not take place when the job can reasonably be done from the ground.

SafeWork NSW and WorkSafe New Zealand

The NSW code, section 4.1, lists what is considered before the climber leaves the ground. The list covers inspecting, adjusting and fitting climbing equipment and PPE, choosing anchor points, and preparing rescue equipment and a rescue plan. It also names two methods of attachment where reasonably practicable, connection hardware that is connected, locked and correctly oriented, and knots that are tied, dressed and pre-loaded. A climbing rope at least twice the length of the highest intended anchor point is on the list too.

The New Zealand code, section 3.2.2, calls for a visual hazard assessment of the tree and the rooted area before climbing. Working techniques and work progression are discussed and understood by ground staff before the climb. Rescue procedures are outlined and understood.