Prompt payment on public contracts: US federal act, a California local rule and the UK 30-day term
The federal Prompt Payment Act adds interest to a late agency payment, California sets 30 days for local agency progress payments, and the UK Procurement Act implies a 30-day payment term.
Checked against the sources at the bottom of this page on October 19, 2026. Rules, fees and pay change: the source has the last word.
This page reports what the official source says. It is not legal advice: ask the office named here.
At a glance
| Place and law | Payment period | Late interest |
|---|---|---|
| US federal, 31 U.S.C. 3902 and 5 CFR 1315.4 | Date in the contract, or 30 days after a proper invoice is received when the contract names none | Rate set by the Treasury Secretary. The Fiscal Service lists 4.75% for July 1 to December 31, 2026 |
| California, Public Contract Code 20104.50 | 30 days after an undisputed and properly submitted payment request on a construction contract | The legal rate in Code of Civil Procedure 685.010(a) |
| United Kingdom, Procurement Act 2023 section 68 | Before the end of 30 days from the invoice or, if later, the date the invoice makes payment due | None stated in the section |
US federal agencies: the Prompt Payment Act
The Bureau of the Fiscal Service says Congress passed the Prompt Payment Act in 1982 to require federal agencies to pay bills on time, pay interest penalties when payments are late, and take discounts. In most cases, when an agency pays a vendor late, it must pay interest.
Title 31, section 3902 sets the interest penalty. An agency head who does not pay a business concern by the required payment date pays interest on the amount due. The rate is the one the Secretary of the Treasury sets and publishes in the Federal Register for payments under 41 U.S.C. 7109. Interest runs from the day after the required payment date to the date of payment.
The section adds several terms:
- A penalty of US$1.00 or more is paid whether or not the business has asked for it.
- Each payment carrying a penalty comes with a notice of the amount, the rate and the period.
- Temporary unavailability of funds does not relieve an agency of the penalty.
- Interest left unpaid after 30 days is added to the principal, and a penalty accrues on the added amount.
- An additional penalty applies if the business made a written demand within 40 days of the payment and the agency did not pay the interest within 10 days of it.
The implementing rule, 5 CFR 1315.4, sets the payment date. Payment is due on the date in the contract, under discount terms, under accelerated payment methods, or 30 days after the start of the payment period when none of these applies. The period starts on receipt of a proper invoice. An invoice is deemed received on the later of the date a proper invoice is actually received and the seventh day after delivery or completion, unless the agency accepted the work earlier. An improper invoice goes back to the vendor no later than 7 days after receipt, with the defects listed.
The Fiscal Service gives the Prompt Payment interest rate for July 1 to December 31, 2026 as 4.75%. It says agencies should pay early when the invoice is proper and early payment is in the government's best interest. Any one of three further conditions must also hold: the invoice is under US$2,500, the payment is to a small business, or the payment relates to an emergency, disaster or military deployment.
California: local agency construction payments
Public Contract Code section 20104.50 applies to local governments. The trigger is a payment request on a construction contract that is undisputed and properly submitted. A local agency that fails to make a progress payment within 30 days after receipt pays the contractor interest at the legal rate in section 685.010(a) of the Code of Civil Procedure. The Legislature calls prompt payment a matter of statewide concern.
The agency reviews each request as soon as practicable. A request found not proper is returned within seven days with a written statement of reasons. Days the agency takes beyond seven reduce the days it has to pay without interest. A local agency includes a city, a county and a city and county. A progress payment includes all payments due contractors except the retention portion of the final payment. Each agency must set the article, or a summary of it, in the terms of any contract it covers.
United Kingdom: Procurement Act 2023, section 68
Section 68 implies payment terms into every public contract entered into by a contracting authority. Three kinds of contract are excluded: a concession contract, a utilities contract awarded by a private utility, and a contract awarded by a school. Any sum due must be paid before the end of the period of 30 days beginning with the day the invoice is received or, if later, the day payment falls due under the invoice.
The 30-day term does not apply if the authority considers the invoice invalid or disputes it. The authority must then tell the payee without undue delay. A valid invoice is an electronic invoice in the required form, or one that sets out the minimum information and meets any contract requirement. The minimum is the invoicing party's name, a description of the goods, services or works, the sum requested and a unique identification number.
A term restricting or overriding the implied terms has no effect. The parties may agree an earlier payment. An appropriate authority may by regulations change the period, but not beyond 30 days. The section came into force on 24 February 2025.
Sources
- Cornell Legal Information Institute, 31 U.S. Code section 3902, interest penalties, read October 19, 2026
- eCFR, 5 CFR 1315.4 Prompt payment standards and required notices to vendors, read October 19, 2026
- US Department of the Treasury, Bureau of the Fiscal Service, Prompt Payment, read October 19, 2026
- California Public Contract Code section 20104.50, public.law mirror of the California Legislature text, read October 19, 2026
- legislation.gov.uk, Procurement Act 2023, section 68, implied payment terms in public contracts, read October 19, 2026