ArbNation Join free

Land clearing in public bids: the pricing units agencies use (lump sum, per acre, per tree)

NCDOT's specification pays clearing and grubbing as a lump sum, supplementary clearing per acre and select trees each. Two NCDOT bid sheets print those units with every bidder's prices, and no average.

Checked against the sources at the bottom of this page on October 15, 2026. Rules, fees and pay change: the source has the last word.

This page reports what the official source says. It is not legal advice: ask the office named here. On the NCDOT tabulations below, clearing is priced three ways: one lump sum for a whole job, a rate per acre, and a rate per tree. NCDOT's Standard Specifications write the three units into the pay items. Two bid sheets show them with prices.

Clearing and grubbing in the specification

NCDOT's 2006 Standard Specifications, Division 2, Section 200, define clearing as the cutting, removal and satisfactory disposal of all wooded vegetation and debris. Grubbing is the complete removal and satisfactory disposal of all grassy vegetative matter, root mat, ball and root, topsoil material high in organic content, and surface debris.

Section 200-7, Measurement and Payment, lists three pay items.

Pay item and unitHow the section measures it
Clearing and Grubbing: lump sumNo measurement is made of clearing and grubbing inside the limits originally staked and within the right of way or easements shown on the original plans
Supplementary Clearing and Grubbing: acreWork the Engineer directs outside the originally staked limits, beyond the right of way or easements, or within environmentally sensitive areas shown on the original plans, paid at the contract unit price per acre and measured horizontally
Select Tree Removal: eachThe actual number of select trees satisfactorily removed from the project

Select trees come into play when the contract includes the item and the clearing and grubbing has reached the original clearing limits. The Engineer may then choose to have select trees removed. They must average at least 4 inches across at a point 2 feet above the ground, and the removal includes the root ball, with backfill unless otherwise directed.

All timber cut during the clearing becomes the property of the Contractor and is removed from the project or disposed of as the section sets out. Weeds, vines, plant stalks, loose rock and small scattered trees count as a minor and incidental part of the clearing and grubbing.

One lump sum for 23 acres: Harnett County

NCDOT Division 6 contract D6D2.POC.010, Land Clearing & Grubbing on SR 1769 (Old Stage Road) in Harnett County, is dated July 23, 2021. Seven bidders priced 14 lines. Line 20, Clearing & Grubbing, 23 Acres, has a quantity of 1 and a unit of lump sum. The seeding and mulching for the same 23 acres is priced per acre, and so is the temporary mulching on 10 acres. Bidders appear as A to G in the order the sheet lists them.

BidderMobilization (lump sum)Clearing & Grubbing, 23 Acres (lump sum)
Bidder AUS$11,758.00US$133,638.05
Bidder BUS$11,875.00US$136,000.00
Bidder CUS$25,000.00US$135,700.00
Bidder DUS$16,000.00US$213,000.00
Bidder EUS$18,950.00US$207,000.00
Bidder FUS$45,000.00US$360,000.00
Bidder GUS$72,948.00US$255,000.00
BidderTemporary Mulching (per acre)Seeding & Mulching (per acre)
Bidder AUS$1,150.00US$2,405.80
Bidder BUS$826.00US$2,215.00
Bidder CUS$200.00US$2,900.00
Bidder DUS$1,375.00US$2,875.00
Bidder EUS$1,000.00US$2,250.00
Bidder FUS$100.00US$1,500.00
Bidder GUS$2,500.00US$3,000.00
BidderPrinted total
Bidder AUS$235,173.93
Bidder BUS$237,780.00
Bidder CUS$278,487.00
Bidder DUS$363,142.50
Bidder EUS$365,134.60
Bidder FUS$473,062.00
Bidder GUS$549,998.00

The other lines are priced per linear foot, ton, pound, cubic yard, square yard and each. Two totals, for Bidder D and Bidder G, carry a double asterisk, and the sheet prints no note explaining it.

Per acre and per tree: Cleveland County

NCDOT Division 12 priced Tree & Brush Cutting & Removal in Cleveland County on bids opened Tuesday, January 25, 2022. The sheet carries 22 lines. The four clearing lines are priced per acre, split into minor clearing of 1 acre or less (10 acres) and major clearing of more than 1 acre (20 acres), on primary and secondary routes. Each bidder prints the same rate on both routes. Three bidders print prices as A, B and C. A fourth bidder's columns are blank, with Non-Responsive in the total row.

BidderMinor clearing, 1 acre or less (per acre)Major clearing, more than 1 acre (per acre)
Bidder AUS$200.00US$300.00
Bidder BUS$600.00US$550.00
Bidder CUS$3,000.00US$8,000.00

The tree lines are priced each, in three diameter bands. Lines 8 to 10 and 14 to 16 repeat the bands for the secondary route with their own prices, and only the primary route is tabled.

  • Felled tree removal, under 12 inches (line 5, 15 each): Bidder A US$125.00; Bidder B US$275.00; Bidder C US$85.00
  • Felled tree removal, 12 to 24 inches (line 6, 15 each): Bidder A US$300.00; Bidder B US$450.00; Bidder C US$190.00
  • Felled tree removal, over 24 inches (line 7, 15 each): Bidder A US$300.00; Bidder B US$650.00; Bidder C US$450.00
  • Hazardous tree removal, under 12 inches (line 11, 30 each): Bidder A US$258.00; Bidder B US$400.00; Bidder C US$140.00
  • Hazardous tree removal, 12 to 24 inches (line 12, 30 each): Bidder A US$500.00; Bidder B US$600.00; Bidder C US$350.00
  • Hazardous tree removal, over 24 inches (line 13, 30 each): Bidder A US$400.00; Bidder B US$800.00; Bidder C US$800.00
  • Emergency mobilization (line 22, 2 each): Bidder A US$1.00; Bidder B US$500.00; Bidder C US$10,000.00
  • Printed totals: Bidder A US$113,932.00; Bidder B US$201,125.00; Bidder C US$540,400.00

The engineer's estimate printed under the sheet is US$169,175.00.

Sources