The North Carolina Department of Transportation printed a bid tabulation on August 22, 2019 for tree removal, stump grinding and overhang clearing in Cumberland and Harnett counties. 6 bidders priced 21 lines. Every price on the sheet is shown below.
Checked against the sources at the bottom of this page on October 15, 2026. Rules, fees and pay change: the source has the last word.
This is one public bid tabulation, as the agency published it. These are government contract prices on one sheet, not market quotes and not advice. Bidders appear as Bidder A to Bidder F, in the order the sheet lists them. The sheet names the firms and is linked below. Other sheets are gathered with the public tree contract bids page.
The contract
| Fact | What the sheet says |
|---|---|
| Agency | North Carolina Department of Transportation |
| Contract ID | D6D2.SBE.005 |
| Project | Tree removal, stump grinding and overhang clearing |
| Route | Various |
| Counties | Cumberland and Harnett |
| WBS number | 6.102619.9 |
| Date printed on the tabulation | August 22, 2019 |
| Bidders on the sheet | 6 |
| Lines priced | 21 |
| Corrected bids | Totals for Bidder B and Bidder D carry the note "Corrected Bid" |
NCDOT small business enterprise rules
The contract number carries the letters SBE. NCDOT's Small Business page says businesses with incomes of less than US$1.5 million, minus materials, are eligible to certify. The Small Business Enterprise Program Guidelines of November 2017 say that only firms with current SBE certification may bid on a project advertised for SBE firms, unless the advertisement makes an exception. They add that the contractor licence and the payment and performance bonds may be waived under G.S. 136-28.10. The sheet does not say which of these were waived on this contract.
Prices as printed
Each bidder wrote one unit price per line, and the sheet prints the department's quantity beside it. Unit price times quantity matches the printed line total in every cell, and the line totals add up to each printed total bid, so the line totals are left out of the tables. Line 19 is priced per linear foot and the mobilization lines by the each.
Unit prices, Bidder A and Bidder B
| Line, item and estimated quantity | Bidder A | Bidder B |
|---|---|---|
| 1. 6 inch diameter tree removal (each, estimated quantity 2) | US$24.00 | US$400.00 |
| 2. 10 inch diameter tree removal (each, estimated quantity 5) | US$86.00 | US$400.00 |
| 3. 15 inch diameter tree removal (each, estimated quantity 10) | US$146.00 | US$425.00 |
| 4. 21 inch diameter tree removal (each, estimated quantity 50) | US$210.00 | US$200.00 |
| 5. 27 inch diameter tree removal (each, estimated quantity 15) | US$310.00 | US$300.00 |
| 6. 33 inch diameter tree removal (each, estimated quantity 5) | US$550.00 | US$1,000.00 |
| 7. 39 inch diameter tree removal (each, estimated quantity 1) | US$1,100.00 | US$2,500.00 |
| 8. 45 inch diameter tree removal (each, estimated quantity 1) | US$1,640.00 | US$2,500.00 |
| 9. 52 inch diameter tree removal (each, estimated quantity 1) | US$1,980.00 | US$3,000.00 |
| 10. Grind stump, 6 inch diameter (each, estimated quantity 1) | US$36.00 | US$100.00 |
| 11. Grind stump, 10 inch diameter (each, estimated quantity 1) | US$58.50 | US$100.00 |
| 12. Grind stump, 15 inch diameter (each, estimated quantity 5) | US$84.55 | US$100.00 |
| 13. Grind stump, 21 inch diameter (each, estimated quantity 10) | US$106.80 | US$50.00 |
| 14. Grind stump, 27 inch diameter (each, estimated quantity 1) | US$133.50 | US$200.00 |
| 15. Grind stump, 33 inch diameter (each, estimated quantity 3) | US$160.20 | US$200.00 |
| 16. Grind stump, 39 inch diameter (each, estimated quantity 2) | US$186.90 | US$300.00 |
| 17. Grind stump, 45 inch diameter (each, estimated quantity 1) | US$218.05 | US$400.00 |
| 18. Grind stump, 52 inch diameter (each, estimated quantity 1) | US$320.00 | US$500.00 |
| 19. Overhang clearing (linear foot, estimated quantity 300) | US$1.24 | US$10.00 |
| 20. Emergency mobilization (each, estimated quantity 1) | US$100.00 | US$1,500.00 |
| 21. Mobilization (each, estimated quantity 40) | US$0.00 | US$200.00 |
Unit prices, Bidder C and Bidder D
| Line, item and estimated quantity | Bidder C | Bidder D |
|---|---|---|
| 1. 6 inch diameter tree removal (each, estimated quantity 2) | US$250.00 | US$100.00 |
| 2. 10 inch diameter tree removal (each, estimated quantity 5) | US$250.00 | US$500.00 |
| 3. 15 inch diameter tree removal (each, estimated quantity 10) | US$250.00 | US$500.00 |
| 4. 21 inch diameter tree removal (each, estimated quantity 50) | US$300.00 | US$500.00 |
| 5. 27 inch diameter tree removal (each, estimated quantity 15) | US$300.00 | US$600.00 |
| 6. 33 inch diameter tree removal (each, estimated quantity 5) | US$400.00 | US$700.00 |
| 7. 39 inch diameter tree removal (each, estimated quantity 1) | US$500.00 | US$1,000.00 |
| 8. 45 inch diameter tree removal (each, estimated quantity 1) | US$600.00 | US$1,000.00 |
| 9. 52 inch diameter tree removal (each, estimated quantity 1) | US$700.00 | US$1,000.00 |
| 10. Grind stump, 6 inch diameter (each, estimated quantity 1) | US$60.00 | US$1.00 |
| 11. Grind stump, 10 inch diameter (each, estimated quantity 1) | US$100.00 | US$1.00 |
| 12. Grind stump, 15 inch diameter (each, estimated quantity 5) | US$300.00 | US$1.00 |
| 13. Grind stump, 21 inch diameter (each, estimated quantity 10) | US$300.00 | US$1.00 |
| 14. Grind stump, 27 inch diameter (each, estimated quantity 1) | US$300.00 | US$1.00 |
| 15. Grind stump, 33 inch diameter (each, estimated quantity 3) | US$400.00 | US$1.00 |
| 16. Grind stump, 39 inch diameter (each, estimated quantity 2) | US$400.00 | US$1.00 |
| 17. Grind stump, 45 inch diameter (each, estimated quantity 1) | US$500.00 | US$1.00 |
| 18. Grind stump, 52 inch diameter (each, estimated quantity 1) | US$800.00 | US$1.00 |
| 19. Overhang clearing (linear foot, estimated quantity 300) | US$5.00 | US$5.00 |
| 20. Emergency mobilization (each, estimated quantity 1) | US$500.00 | US$1.00 |
| 21. Mobilization (each, estimated quantity 40) | US$800.00 | US$900.00 |
Unit prices, Bidder E and Bidder F
| Line, item and estimated quantity | Bidder E | Bidder F |
|---|---|---|
| 1. 6 inch diameter tree removal (each, estimated quantity 2) | US$400.00 | US$175.00 |
| 2. 10 inch diameter tree removal (each, estimated quantity 5) | US$600.00 | US$250.00 |
| 3. 15 inch diameter tree removal (each, estimated quantity 10) | US$700.00 | US$375.00 |
| 4. 21 inch diameter tree removal (each, estimated quantity 50) | US$800.00 | US$475.00 |
| 5. 27 inch diameter tree removal (each, estimated quantity 15) | US$900.00 | US$600.00 |
| 6. 33 inch diameter tree removal (each, estimated quantity 5) | US$1,000.00 | US$700.00 |
| 7. 39 inch diameter tree removal (each, estimated quantity 1) | US$1,200.00 | US$825.00 |
| 8. 45 inch diameter tree removal (each, estimated quantity 1) | US$1,500.00 | US$950.00 |
| 9. 52 inch diameter tree removal (each, estimated quantity 1) | US$1,800.00 | US$1,200.00 |
| 10. Grind stump, 6 inch diameter (each, estimated quantity 1) | US$60.00 | US$75.00 |
| 11. Grind stump, 10 inch diameter (each, estimated quantity 1) | US$100.00 | US$100.00 |
| 12. Grind stump, 15 inch diameter (each, estimated quantity 5) | US$150.00 | US$125.00 |
| 13. Grind stump, 21 inch diameter (each, estimated quantity 10) | US$200.00 | US$125.00 |
| 14. Grind stump, 27 inch diameter (each, estimated quantity 1) | US$250.00 | US$225.00 |
| 15. Grind stump, 33 inch diameter (each, estimated quantity 3) | US$250.00 | US$250.00 |
| 16. Grind stump, 39 inch diameter (each, estimated quantity 2) | US$250.00 | US$250.00 |
| 17. Grind stump, 45 inch diameter (each, estimated quantity 1) | US$300.00 | US$250.00 |
| 18. Grind stump, 52 inch diameter (each, estimated quantity 1) | US$500.00 | US$350.00 |
| 19. Overhang clearing (linear foot, estimated quantity 300) | US$10.00 | US$7.00 |
| 20. Emergency mobilization (each, estimated quantity 1) | US$100.00 | US$5,000.00 |
| 21. Mobilization (each, estimated quantity 40) | US$800.00 | US$1,475.00 |
Total bid as printed
| Bidder | Total bid |
|---|---|
| Bidder A | US$28,141.20 |
| Bidder B | US$50,550.00, corrected bid |
| Bidder C | US$69,810.00 |
| Bidder D | US$85,726.00, corrected bid |
| Bidder E | US$114,110.00 |
| Bidder F | US$114,800.00 |
Mobilization, estimated quantity 40, totals US$0.00 for Bidder A, US$8,000.00 for B, US$32,000.00 for C, US$36,000.00 for D, US$32,000.00 for E and US$59,000.00 for F. Entries printed at US$1.00 or less: Bidder D on lines 10 to 18 and on line 20, and US$0.00 for Bidder A on line 21.
Where to read the sheet
The agency's bid tabulation is the source for every price on this page. The small business enterprise rules are at the NCDOT small business enterprise page and in the SBE Program Guidelines.
Sources
- North Carolina Department of Transportation, Division 6 bid tabulation D6D2.SBE.005, August 2019, read October 15, 2026
- North Carolina Department of Transportation, small business enterprise certification page, read October 15, 2026
- North Carolina Department of Transportation, Small Business Enterprise Program Guidelines, November 2017, read October 15, 2026