Public bid words: DBH bands, unit price, on-call, mobilization and traffic control
Bid sheets use a short set of words: DBH band, unit price, lump sum, on-call, mobilization and traffic control. Definitions here come from a Clark County sheet, North Carolina's specifications, the federal traffic control manual and a Forest Service glossary.
Checked against the sources at the bottom of this page on October 21, 2026. Rules, fees and pay change: the source has the last word.
The words below come from four documents. Clark County, Washington, tabulated Bid 2714, on-call hazard tree removal, with three bidders priced line by line. The North Carolina Department of Transportation defines its contract terms in Section 101 of its 2012 Standard Specifications. The Federal Highway Administration sets out temporary traffic control in Part 6 of the 11th Edition of the Manual on Uniform Traffic Control Devices. The USDA Forest Service Forest Inventory and Analysis program defines tree diameter.
Words on the tree lines
| Term | What the document records |
|---|---|
| DBH | The Forest Inventory and Analysis glossary defines diameter at breast height (d.b.h.) as the diameter of a tree stem measured 4.5 feet (1.37 m) above ground, outside the bark. It adds that the point of measurement may vary for abnormally formed trees. The Clark County sheet prints "in DBH" after each size range and does not spell the term out. |
| DBH band | A size range with its own price line. Bid 2714 prices tree removal in three bands: 6.0 to 15.9 inches, 16.0 to 30.0 inches, and over 30 inches. Stump grinding and removal uses the same three bands. |
| On-call | The word in the title of Bid 2714, on-call hazard tree removal. The sheet lists work lines with an estimated quantity each, not named trees: 15 removals in the first band, 15 in the second and 6 in the third for developed parks and lands. |
| Unit, estimated quantity, unit price, total | The four column headings for each bidder on the Clark sheet. The unit for every line is EA, each. The total is the estimated quantity times the unit price, such as 15 times US$200.00 for US$3,000.00. |
| Developed and undeveloped parks and lands | The two headings that split the Clark sheet. The same removal band is priced under each. Bidder A priced the 6.0 to 15.9 inch band at US$200.00 for developed land and US$150.00 for undeveloped land. |
| Debris removal line | A separate line on the Clark sheet, priced each, for removal of debris after a tree removal and after a stump grinding. On the developed land lines, Bidder A priced both debris lines at US$75.00 each, Bidder B at US$150.00 and US$100.00, and Bidder C at US$600.00 and US$255.00. |
| Sub-total and net total bid | The Clark sheet adds the line totals, then adds Washington State sales tax at 8.4 percent. Bidder A shows US$24,675.00 plus US$2,072.70 tax for a net total of US$26,747.70. |
Words on the contract
The North Carolina specifications open with a rule: whenever a term defined in Section 101 appears in the contract documents or plans, it carries the meaning given there.
| Term | Definition as printed |
|---|---|
| Contract item, pay item | A unit of work the contract describes and prices, either per unit or as a lump sum. The two names mean the same thing. |
| Contract unit price | The unit bid price for a unit item that the contractor submitted in the proposal. |
| Contract lump sum price | The amount bid for a lump sum item that the contractor submitted in the proposal. |
| Mobilization | "The work described in Article 800-1." Section 101 gives no other wording. |
| Proposal | The electronic or paper document the Department provides, which the bidder uses to develop an offer to perform the work at designated bid prices. |
| Bid bond or bid deposit | The security furnished with a bid as a guaranty that the bidder will furnish the required bonds and execute such documents as may be required if the bid is accepted. |
| Award | The Department's decision to accept the bid of the lowest responsible responsive bidder for work that is subject to payment and performance bonds and the other conditions provided by law, the proposal and the specifications. |
| Prebid conference | A conference held before bids are accepted, where Department representatives give information and answer questions from interested parties. |
| Extra work | Work found necessary or desirable to complete the contract that the contract unit or lump sum prices do not pay for. It does not include work that is incidental to a priced item. |
| Additional work | Work that results from a change to the contract and for which there are existing contract unit prices. |
| Unbalanced bid price | A unit or lump sum price that does not reflect reasonable actual costs for the item plus a reasonable share of the bidder's profit, overhead and other indirect costs. |
Traffic control
Part 6 of the MUTCD uses TTC for temporary traffic control and says a TTC plan describes the TTC measures to be used for facilitating road users through a work zone or an incident area. The needs and control of all road users through a TTC zone are part of highway construction, utility work, maintenance operations and the management of traffic incidents. The TTC selected for each situation depends on the type of highway, road user conditions, the duration of the operation, physical constraints and how near the work space is to road users.
The Manual calls each TTC zone different and describes plans that run from very detailed to a simple reference to typical drawings. On low-volume and special purpose roads, especially for shorter-term work and lower-speed roads, maintenance vehicle warning flashers, a limited number of signs, or a single flagger could be adequate. Section 6B.01 says traffic control planning should be completed for all highway construction, utility work, maintenance operations and incident management, including minor maintenance and utility projects, prior to occupying the TTC zone. Bid 2714 has no traffic control line.
Words around the bid
Clark County's bids page lists each solicitation with its bid number, opening date, pre-bid conference, attachments and award. Attachments include a plan holder list, a tab sheet, a bid inquiry log and addenda. The page prints an engineer's estimate field, which reads N/A on the bids listed there. It also prints who was awarded the bid and the total amount. A tab sheet, such as the one for Bid 2714, shows every bidder's prices.
For a worked reading of one sheet, see the Clark County Bid 2714 page. How to find sheets like it is covered in the guide to finding public tree bid tabulations.
Sources
- Clark County, Washington, Bid 2714 on-call hazard tree removal, tab sheet, opened October 27, 2020, read October 21, 2026
- Clark County, Washington, Bids page (purchasing), read October 21, 2026
- North Carolina Department of Transportation, 2012 Standard Specifications, Section 101 Definitions of Terms, read October 21, 2026
- Federal Highway Administration, Manual on Uniform Traffic Control Devices, 11th Edition, Part 6 Temporary Traffic Control, read October 21, 2026
- USDA Forest Service, Forest Inventory and Analysis Glossary: Standard Terminology, December 11, 2023, read October 21, 2026