Root zones and cutting roots in tree protection rules: Portland, Toronto, Sydney and Seattle
Portland sets a root protection zone of one foot of radius per inch of trunk diameter. Toronto lists cutting roots among the acts that injure a protected tree. Sydney grades intrusion at 10 and 20 percent. Seattle sets a limit at roots over 2 inches.
Checked against the sources at the bottom of this page on October 19, 2026. Rules, fees and pay change: the source has the last word.
This page reports what the official source says. It is not legal advice: ask the office named here. The rules here come from one US city code, one Canadian city code, one Australian council guide and one US city sidewalk repair page, on the ground around a protected tree and on cutting roots. None of the four gives a single figure for how many roots may be cut. Portland, Toronto and Sydney protect an area instead, and treat work inside that area as something to be assessed, permitted or kept out. Other protection standards are in the trees on building sites guide.
The rules side by side
| Place and source | How the protected ground is sized | Work inside the protected ground |
|---|---|---|
| Portland, Oregon: City Code 11.60.030, amended effective January 1, 2025 | A root protection zone with a minimum radius of one foot, measured horizontally from the face of the trunk, for each inch of tree diameter | Existing structures, paving and utilities in the zone may remain. New encroachments are allowed only if all of them together are under 25 percent of the remaining zone area and none is closer than half the required radius. |
| Toronto, Ontario: Municipal Code Chapter 813, Trees, and the city's tree and ravine permit page | A tree protection zone read from a table by trunk diameter at 1.4 metres. For a tree on private property it runs from 2.4 metres for a 30 to 40 centimetre trunk to 6.0 metres for 91 to 100 centimetres. | The city lists cutting, breaking, tearing, crushing, exposing or stripping a tree's roots among the acts that can injure it. A permit is needed to injure a protected tree. |
| City of Sydney, New South Wales: Tree guidelines for pruning, reporting and using an arborist, December 2025 | A notional root zone and a structural root zone, worked out under Australian Standard 4970 (2025) | Minor is intrusion of up to 10 percent of the notional root zone, with no recent encroachments and outside the structural root zone. Moderate is over 10 and up to 20 percent. Major is over 20 percent, or any intrusion into the structural root zone. |
| Seattle, Washington: SDOT sidewalk repair page | No zone is sized. The limit is a root diameter. | Before roots over 2 inches in diameter are pruned, an SDOT Arborist must evaluate the effect on the tree's health and public safety. |
Portland
Chapter 11.60 of the Portland City Code gives two paths. On the prescriptive path the zone is the radius above. The code names fencing of at least six feet of metal chain link on eight-foot posts at the edge of the zone, and signs stating penalties. It lists what is prohibited inside the zone: ground disturbance and construction activity including vehicle access, storage, stockpiling, buildings, paving, underground utilities, excavation or fill, and trenching. It counts in-ground irrigation as an encroachment and says landscaping required under Title 33 is not one. On the performance path, an arborist who has visited the site prepares an alternative zone based on the tree's size, location, extent of root cover, species, health and past impacts. The arborist signs the plan, and the city may have it peer reviewed or require a performance guarantee. Section 11.60.040 of the same chapter says pruning or root cutting must follow proper arboricultural practices, using clean and sharp tools.
Chapter 11.50 of the same code ties the rules to work near roots. It covers development with ground disturbance inside the root protection zone of a private tree 12 or more inches in diameter, or a city tree six or more inches in diameter. It also names a staging area over 100 square feet on unpaved ground inside such a zone.
Toronto
Chapter 813 of the Toronto Municipal Code (the PDF is dated May 12, 2022) defines injure as any act that will harm a tree's health in any manner, including failure to protect it to the General Manager's standards. It bars injuring, destroying or removing a tree with at least one stem of 30 centimetres or more, measured at 1.4 metres, without a permit. Its permit conditions say an injury permit is carried out by or under the supervision of an arborist, only after a building or demolition permit, and with tree protection barriers installed before work starts. The city's permit page gives the table of tree protection zones by trunk diameter. For trees in ravines and natural areas the sizes in the table are double for trunks of 10 centimetres or more, or the dripline if that is greater. If construction on site will affect the zone, a permit to remove or injure is needed. If it will not, the city expects a tree protection plan made with an arborist. The permit page also states that roots do not cause lifts or cracks in properly built and well-kept infrastructure.
Sydney
The City of Sydney guide says Australian Standard 4970 gives formulae for two zones. The tree protection zone is the minimum area needed for a tree's health and can extend well beyond the crown. The structural root zone is the smaller area around the base that usually holds most of the large structural roots. Moderate intrusion needs the consultant arborist to review the impact and show the tree will stay viable. Major intrusion needs alternative designs to be explored. The guide says that where the zone is reduced in one place it should be offset by an equal extension in another contiguous area, to avoid a net loss of soil area and volume.
Gaps in the rules
None of these pages states a share of roots that may be cut from a tree. The Portland, Toronto and Sydney pages also give no diameter of root below which cutting is free of consequence. Portland and Sydney express the limit as a share of an area. Toronto leaves the root question to the permit. Sizes, fees and procedures belong to the offices that publish them.
Sources
- City of Portland, Oregon, City Code Chapter 11.60 Technical Specifications, read October 9, 2026
- City of Portland, Oregon, City Code Chapter 11.50 Trees in Development Situations, read October 9, 2026
- City of Toronto, Municipal Code Chapter 813 Trees (PDF dated May 12, 2022), read October 9, 2026
- City of Toronto, When to Apply For a Tree or Ravine Permit, read October 9, 2026
- City of Sydney, Tree guidelines for pruning, reporting and using an arborist, December 2025, read October 9, 2026
- City of Seattle, Department of Transportation, Sidewalk Repair page, read October 19, 2026