State vegetation management rules: what Missouri, Maryland, Indiana, Oregon and California require of utilities

Five state rules put duties on utility vegetation programmes: Missouri and Maryland set inspection or trim cycles, Indiana sets notice, Oregon sets clearances and California sets Rule 35 of General Order 95.

Checked against the sources at the bottom of this page on October 15, 2026. Rules, fees and pay change: the source has the last word.

This page reports what the official source says. It is not legal advice: ask the office named here.

The five rules in brief

Citation and what each rule covers
State and citationPlan, cycle, notice and report
Missouri, 20 CSR 4240-23.030 (Public Service Commission)Written standards filed with the commission; a named vegetation manager; a visual inspection every 2 years urban and 3 years rural; notice 7 to 90 days ahead; annual report due April 1
Maryland, COMAR 20.50.12.09 (Public Service Commission)Programme filed with the Commission; a 4-year or 5-year trim cycle with percentage milestones; notice 7 to 120 days ahead; annual performance report
Indiana, 170 IAC 4-9-4 (Utility Regulatory Commission)Notice at least two calendar weeks before routine vegetation management; no cycle or clearance in this section
Oregon, OAR 860-024-0016 (Public Utility Commission)A vegetation management programme with records; minimum clearances by voltage; the Commission may require trim cycles if clearances slip
California, General Order 95, Rule 35 (Public Utilities Commission)Clearances from Table 1, Cases 13 and 14; removal of dead or diseased trees that could fall into a span; a good-faith permission exception

Missouri

Rule 20 CSR 4240-23.030, in the Code of State Regulations edition of August 31, 2026, was filed December 14, 2007, effective June 30, 2008, and moved to its current number effective August 28, 2019. It applies to distribution conductors of 600 volts and higher that an electrical corporation owns in whole or in part. Each corporation must employ a vegetation manager whose name and contact details appear on its website and on every notice.

The rule defines urban as 35 or more customers per circuit mile and rural as fewer. A visual inspection is required at least every two years in urban areas and every three years in rural areas. Each corporation files its own standards with the commission and files any change 30 days before it takes effect. It reports its own violations within 30 days. Trimmings from regular cycle work must be removed within five business days, unless the owner consents to leave them or a storm caused the outage.

Owners and occupants get notice at least 7 days and not more than 90 days before planned work. Counties and municipalities get written notice two months ahead. The annual report is due April 1 and covers expenditures, the budget, circuits trimmed and miles, with an officer's affidavit. Section 9 also sets milestone percentages: 100 percent of urban distribution miles by the four-year anniversary of the rule and 100 percent of rural miles by the six-year anniversary, then 25 percent of urban miles each year.

Maryland

COMAR 20.50.12.09 sets minimum requirements that do not stop a utility from adopting more aggressive standards. A utility files its programme with the Commission within 90 days of the regulation's effective date. It files any change at least 30 days before implementing it, unless exigent circumstances apply. Work follows the standards for Maryland Licensed Tree Experts.

A utility on a 4-year trim cycle must treat at least 15 percent of its distribution miles by month 12, 40 percent by month 24, 70 percent by month 36 and 100 percent at year four. A 5-year cycle runs 12, 32, 56, 75 and 100 percent. Notice to owners or occupants goes out at least 7 days and not more than 120 days ahead, and may not be a bill insert alone. For each county and municipality, notice goes out at least two months ahead.

For readily identified tree removals on residential property, the utility must contact the owner first. Owners may ask for direct communication with a utility vegetation representative, who must respond within 7 business days. Violations are reported to the Commission within 60 days of discovery. The annual performance report lists expenditures, budget, circuits and miles trimmed.

Indiana

170 IAC 4-9-4, filed in 2012 and readopted April 11, 2019, covers notice. A utility gives customers and property owners notice at least two calendar weeks before routine vegetation management. Exceptions apply where the utility holds a written easement, government permit, contract or court order that expressly gives the right, and during an emergency or storm event.

The utility must make at least one attempt to reach the customer in person or by telephone and at least one attempt in writing. The written notice carries the heading TREE TRIMMING NOTICE, the date delivered or mailed, and the commission's and utility's website addresses. Receipt of the notice starts a two-week window for calculating implied consent. A customer may ask for the estimated day within three calendar days and the utility provides it at least three business days ahead. A property owner can instead be notified by newspaper publication in the county.

Oregon and California

OAR 860-024-0016 requires each operator to have a vegetation management programme and records that it makes available to the Commission on request. The minimum clearances under reasonably anticipated operating conditions are in the table. The rule also defines readily climbable vegetation and requires an operator to trim or remove it to minimize the likelihood that a member of the public can reach a high voltage conductor. The rule was amended effective September 22, 2022.

California's Rule 35 of General Order 95 says that where overhead conductors pass through trees, the minimum clearances in Table 1, Cases 13 and 14, must be kept. Dead, rotten or diseased trees that overhang or lean toward a span and may fall into it should be removed once the company has actual knowledge. Circuits at 750 volts or less should be kept clear of vegetation in new construction and when rebuilt, whenever practicable. The rule says contact between vegetation and a conductor does not by itself breach the rule. One exception covers a good-faith effort to get permission, shown by an attempted personal contact and a written communication. Another covers mature trees whose trunks and limbs sit more than six inches from primary distribution conductors and are strong enough to stay out of that space.

Clearances side by side

Minimum clearances in the Missouri and Oregon rules
Conductor voltageMissouriOregon
Above 200,000 V15 ft, or the edge of the right of way if closer (above 50,000 V)10 ft
50,001 to 200,000 V15 ft, or the edge of the right of way if closer7.5 ft
600 to 50,000 V10 ft, or the edge of the right of way if closer5 ft, or 3 ft if not readily climbable

Maryland sets its horizontal clearance as the greater of 15 feet or the growth expected over the trim cycle above 34.5 kV, and 10 feet or that growth at 14 to 34.5 kV, with growth alone below 14 kV. The voltage bands differ between states, so a row compares only the nearest bands. Missouri exempts mature trees on conductors at or below 35,000 volts whose trunks or limbs are strong enough. Maryland allows mature trees to be exempt at the utility's reasonable discretion at 34.5 kV and below. Oregon accepts small branches and new growth inside the 5-foot clearance if the vegetation does not come within six inches of the conductor.