Missouri's Public Service Commission sets vegetation standards for electric utilities in 20 CSR 4240-23.030, with notice 7 to 90 days ahead. Ameren Missouri says the service line from the pole to the house is the owner's.

This page is for tree owners. It reports what the named sources say and is not advice about your tree: for that, ask a qualified arborist or one of the offices under Who to call.

Checked against the sources at the bottom of this page on October 21, 2026. Rules, fees and pay change: the source has the last word.

This page reports what the official source says. It is not legal advice: ask the office named here. Missouri's rule is 20 CSR 4240-23.030, Electrical Corporation Vegetation Management Standards and Reporting Requirements, from the Public Service Commission. Ameren Missouri's service page and an April 23, 2025 company release cover the utility's side.

The Commission's rule

The rule sets minimum standards for the vegetation management programs of electrical corporations. It covers distribution conductors of 600 volts and higher that the utility owns in whole or in part. Each utility must have a vegetation management plan, keep records for the Commission, and employ a vegetation manager whose name and contact details appear on its website and on every notice.

  • Inspection: a visual inspection at least once every 2 years for urban distribution conductors and once every 3 years for rural ones. Urban means 35 or more customers per circuit mile, and rural means fewer than 35.
  • Standards: work follows ANSI Z133.1-2006 and Part 1 of ANSI A300-2001, as incorporated by the rule.
  • Hazards: when the utility learns of vegetation that is an imminent threat, it promptly removes or remedies it. If that means crossing property where it holds no easement, it makes reasonable efforts to get the owner's permission.
  • Cleanup: trimmings and cut vegetation from regular maintenance are removed within 5 business days, unless the owner consents to leaving them or the work followed a storm outage.

Notice

The utility makes a diligent attempt to notify affected property owners or occupants. Notice at least 7 days and no more than 90 days before planned work satisfies the rule. It goes by direct mailing, door hanger, postcard, bill insert, personal contact or another Commission-approved method.

The utility keeps a record of the dates, content and addresses of each notice until the next cycle. It also writes to a primary contact for each affected county and municipality at least 2 months ahead, with planned dates and locations.

Ameren Missouri

Ameren Missouri's Trees and Your Energy Service page says it trims trees only in right-of-way areas and easements. The release repeats that Ameren trims trees and clears brush on rights-of-way and easements along main power lines, and that customers keep trees maintained along their service drop, the line from the main power line to the home.

  • Higher voltage: only qualified line clearance tree contractors are allowed to work within 10 feet of higher voltage lines.
  • Disconnection: for tree work near a service drop, Ameren can disconnect service so the work is done safely. The release gives 800-552-7583 for a temporary disconnection or to report hazards.
  • Reach of the program: Ameren contracts with more than 300 tree-trimming crews and maintains vegetation along more than 13,000 miles of line in Missouri and Illinois.
  • Debris: regular maintenance crews normally remove debris unless the owner makes other arrangements. Emergency crews after storm damage often leave it for the owner to dispose of.
  • Help with costs: some local municipalities and nonprofit organizations may offer financial assistance or tree removal for qualifying individuals.

The same Ameren page serves both Missouri and Illinois customers, so its wording is not specific to this state.