Trees and airport obstruction rules: FAA Part 77 and the UK CAA safeguarding page

Under 14 CFR Part 77, the FAA's obstruction standards cover objects of natural growth as well as structures. They are measured from imaginary surfaces around each runway. UK CAA guidance says aerodrome licensees should safeguard obstacle limitation surfaces.

Checked against the sources at the bottom of this page on October 16, 2026. Rules, fees and pay change: the source has the last word.

This page reports what the official source says. It is not legal advice: ask the office named here. The text is 14 CFR Part 77, Safe, Efficient Use, and Preservation of the Navigable Airspace, as published in the eCFR. Part 77 sets notice requirements for construction and alteration, the standards that decide what counts as an obstruction, and the process of aeronautical studies.

Scope and notice

Section 77.1 gives the purpose of Part 77: requirements to notify the FAA of certain construction or alteration, standards to determine obstructions to air navigation, a process for aeronautical studies, and a process to petition for review. Section 77.13 applies the obstruction standards to any object of natural growth, terrain, or permanent or temporary construction or alteration.

The notice requirement is worded differently. Section 77.9 lists the construction or alteration that needs notice, and does not mention natural growth. Form 7460-1 goes to the FAA at least 45 days before the start date or the filing of a construction permit application, under section 77.7. The FAA's Obstruction Evaluation / Airport Airspace Analysis (OE3A) portal is the filing system for these notices.

The OE3A page carried a notice that, because of a government shutdown, the FAA was unable to accept new Part 77 notices and processed earlier cases on a limited basis. It added that pending a determination all submittals should be presumed a hazard to air navigation.

Obstruction standards in section 77.17

Section 77.17 treats an existing or future object as an obstruction if it is higher than any of these.

  • 499 feet above ground level at the site of the object.
  • 200 feet above ground level, or the established airport elevation if that is higher, within 3 nautical miles of the reference point of an airport whose longest runway is over 3,200 feet. The height rises 100 feet per additional nautical mile, up to a maximum of 499 feet.
  • A height within a terminal obstacle clearance area, which includes initial approach, departure and circling approach areas, that cuts the vertical distance to the minimum instrument flight altitude below the required clearance.
  • A height within an en route obstacle clearance area of a Federal Airway or approved off-airway route that would raise the minimum obstacle clearance altitude.
  • The surface of a takeoff and landing area, or any imaginary surface set in sections 77.19, 77.21 or 77.23. The takeoff or landing area itself is not an obstruction.

Under section 77.15(b), objects that exceed the standards are presumed hazards to air navigation until further aeronautical study concludes otherwise.

Civil airport imaginary surfaces

SurfaceSection 77.19 dimensions
HorizontalA plane 150 feet above the established airport elevation, with arcs of 5,000 feet for utility or visual runways and 10,000 feet for all other runways
ConicalExtends outward and upward from the edge of the horizontal surface at 20 to 1 for 4,000 feet
PrimaryCentered on the runway and extending 200 feet beyond a runway with a prepared hard surface. Width is 250, 500 or 1,000 feet, depending on runway type and approach
Approach20 to 1 for 5,000 feet for utility and visual runways. 34 to 1 for 10,000 feet for non-precision instrument runways other than utility. For precision instrument runways, 50 to 1 for 10,000 feet then 40 to 1 for 40,000 feet
Transitional7 to 1 outward and upward from the sides of the primary and approach surfaces

Section 77.9 sets notice triggers: construction or alteration more than 200 feet above ground level, or one that exceeds an imaginary surface at set slopes. Those are 100 to 1 for 20,000 feet from the nearest runway point at airports whose longest runway exceeds 3,200 feet, and 50 to 1 for 10,000 feet at shorter-runway airports. Heliports use 25 to 1 for 5,000 feet. Military airports and heliports have separate surfaces in sections 77.21 and 77.23.

Aeronautical studies and determinations

An aeronautical study decides whether a proposal is a hazard to air navigation. The FAA issues a Determination of Hazard when the study finds the proposal exceeds an obstruction standard and would have a "substantial aeronautical impact". It issues a Determination of No Hazard when a standard is exceeded without that impact, sometimes with conditions, limits or marking and lighting recommendations, or when no standard is exceeded. A determination takes effect 40 days after issue where discretionary review applies. A Determination of No Hazard expires 18 months after its effective date unless extended.

United Kingdom: UK CAA safeguarding page

The UK Civil Aviation Authority's Safeguarding of IFP page says it is the published advice of the UK Government that all aerodromes should be safeguarded. CAP 738, Safeguarding of Aerodromes, guides those responsible for an aerodrome on assessing what a proposed development or construction might do to its operation. The page ties the information needed for that assessment to CAP 168, Licensing of Aerodromes, which it says reflects ICAO Annex 14 Volume I. Aerodrome licensees "should ensure" that the obstacle limitation surfaces are safeguarded against proposed development.

The CAA page adds that instrument flight procedure design needs a separate safeguarding assessment, against current and possible future procedures, by a UK Approved Procedure Design Organisation. From 1 August 2019 the CAA no longer provides that assessment service. Related guides cover rail and pipeline corridor work and drone rules near sites.

Sources