USACE debris missions: what the Corps does after a disaster
The U.S. Army Corps of Engineers coordinates Emergency Support Function 3 and takes debris missions when FEMA assigns them. In the 2025 Los Angeles fire mission it cleared more than 9,500 properties and 2.6 million tons of debris.
Checked against the sources at the bottom of this page on October 21, 2026. Rules, fees and pay change: the source has the last word.
The Corps in the federal response framework
FEMA's Emergency Support Function 3 annex, dated June 2016, names the Department of Defense and the U.S. Army Corps of Engineers (USACE) as both ESF Coordinator and primary agency for Public Works and Engineering. Local, state, tribal and territorial governments remain responsible for their own public works and infrastructures and have the primary responsibility for mitigation, preparedness, response and recovery. When ESF 3 is activated, the primary agency sets work priorities with those governments and in coordination with FEMA.
The annex lists the debris tasks under the Infrastructure Systems core capability. ESF 3 manages, monitors or gives technical advice on the clearance, removal and disposal of debris from public property, and on reopening ground and water routes into affected areas. For ESF 3 purposes, debris includes general construction debris that may hold asbestos or paint, livestock or poultry carcasses and plant materials. Under Critical Transportation it also clears debris from roads to support response operations. After a chemical, biological, radiological or nuclear blast, ESF 10 takes over leadership for the contaminated debris once the emergency phase ends. The annex says pre-awarded contracts and other emergency contracting vehicles are used to draw on private-sector capability.
Waterways and flood control works
The FEMA Public Assistance Program and Policy Guide, Version 5.0, effective January 6, 2025, sets out where USACE debris authority sits.
- USACE has primary responsibility for removing debris from federally maintained navigable channels and waterways.
- Section 202 of the Water Resources Development Act of 1976 authorizes USACE to remove debris from federally maintained commercial harbors and the water areas next to them.
- Sections 15, 19 and 20 of the River and Harbor Act of 1899 authorize USACE to remove sunken vessels and other obstructions from navigable waterways under emergency conditions.
- USACE policy is to oversee removal of a sunken vessel by an identifiable owner, operator or lessee if the vessel is in or likely to be moved into a federal navigation channel. The Corps removes a vessel under its emergency authorities only if the owner cannot be identified or cannot remove it in a timely and safe manner.
The FEMA guide lists debris removal from federally maintained navigable waterways as ineligible for Public Assistance funding, and says the Coast Guard and USACE have specific authorities for removing hazardous substances, vessels and other obstructions from them. Flood control works in the USACE Rehabilitation and Inspection Program are different. For those, debris removal is eligible for Public Assistance, but USACE does not reimburse applicants for it. The guide says USACE conducts the work itself when necessary.
The ESF 3 annex adds a waterway task on the federal side: rapid stabilization and reestablishment of critical waterways, channels and ports, including vessel removal, significant marine debris removal, emergency dredging and hydrographic surveys.
A mission on private property: Los Angeles, 2025
A U.S. Army article on the Los Angeles wildfire recovery records a 2025 private-property mission. USACE is the lead agency for ESF 3, which also covers temporary power, temporary housing, critical infrastructure assessment and temporary public facilities. FEMA issued a regional activation mission to USACE on January 10, 2025. About a week later it issued a mission assignment for private property debris removal at the Eaton and Palisades fire areas.
The work ran in phases. The Environmental Protection Agency first removed household hazardous materials. USACE began Phase 2 debris removal on February 11. FEMA set the scope: structural ash and debris, six inches of soil within the ash footprint, and structural foundations.
| Item | Figure |
|---|---|
| Properties cleared | More than 9,500 |
| Debris removed | More than 2.6 million tons, in about six months |
| Personnel deployed over seven months | More than 1,400, including 97 military members and more than 1,300 government civilians |
| Exposure hours | 3.7 million |
| Total recordable incident rate | 0.59, against an industry average of 4.5 |
| Temporary staging sites | Four, used to sort, handle and recycle debris |
| Last private property work | Early September, about four months ahead of the one-year commitment |
USACE also cleared special inclusion properties such as schools, religious institutions, parks and nonprofits. Government representatives stood at every parcel. An issue resolution team handled scope changes as guidance changed, and a debris call center took questions from residents. USACE also explained the right-of-entry process at recovery centers, community meetings and property walkthroughs.
Sources
- U.S. Army, article on the USACE Los Angeles wildfire debris mission, army.mil article 289056, read October 21, 2026
- FEMA, Emergency Support Function #3, Public Works and Engineering Annex, June 2016, read October 21, 2026
- FEMA, Public Assistance Program and Policy Guide, Version 5.0, effective January 6, 2025, pages 119 and following, read October 21, 2026, state-hosted copy from Montana Disaster and Emergency Services