Clause 52.17 of the Victoria Planning Provisions makes a permit the rule for removing, destroying or lopping native vegetation, with a table of exemptions. Queensland and New South Wales use separate clearing frameworks.

Checked against the sources at the bottom of this page on October 19, 2026. Rules, fees and pay change: the source has the last word.

This page reports what the official source says. It is not legal advice: ask the office named here. The Pyrenees Shire Council copy of clause 52.17 carries the date 12 December 2017 and the amendment code VC138. Later planning scheme amendments may have changed the text.

Purpose of clause 52.17

The clause aims for no net loss to biodiversity from removing, destroying or lopping native vegetation. It applies the three steps in the Department's 2017 Guidelines for the removal, destruction or lopping of native vegetation. The first is to avoid the removal. The second is to minimise impacts that cannot be avoided. The last is an offset for the biodiversity impact if a permit is granted. A second purpose is to manage removal so that land and water degradation is kept down.

Permit requirement in clause 52.17-1

Clause 52.17-1 states that a permit is required to remove, destroy or lop native vegetation, including dead native vegetation. Three cases fall outside that rule:

  • Where the table of exemptions in clause 52.17-7 says a permit is not required.
  • Where a native vegetation precinct plan for the land is in the scheme and listed in the schedule to clause 52.16.
  • For native vegetation specified in the schedule to clause 52.17.

Applications, offsets and decisions

Clause 52.17-2 sends applications to the Guidelines for their requirements. Under clause 52.17-4 the responsible authority must consider the decision guidelines in clause 65 and those in the Guidelines. Clause 52.17-5 requires the biodiversity impact of a permitted removal to be offset under the Guidelines. The permit conditions must name the offset and the timing for securing it.

Clause 52.17-3 covers permits granted under a property vegetation plan. Each carries an expiry condition. The permit lapses if the work does not start within two years of the permit date or is not finished within ten years.

Exemptions in clause 52.17-7

The table opens with the line "The requirement to obtain a permit does not apply to". It runs to more than 30 entries, among them conservation work, Crown land, grazing, timber harvesting, surveying, railways and utility installations. The nine entries below each carry their own limits.

Selected exemptions in clause 52.17-7
EntryWording and limits
Dead native vegetationNative vegetation that is dead. The exemption does not cover a standing dead tree with a trunk diameter of 40 centimetres or more at 1.3 metres above ground.
Emergency worksRemoval or lopping by or for a public authority or council to create emergency access. Also removal or lopping where the vegetation presents an immediate risk of personal injury or damage to property. Only the part that presents the immediate risk is covered.
Lopping and pruning for maintenanceMaintenance lopping or pruning, provided no more than one third of the foliage of each plant is taken. It does not cover the trunk of a native tree or vegetation on a roadside or railway reservation.
FencesThe minimum extent needed to operate or maintain an existing fence, or to build a boundary fence between properties in different ownership. Clearing along both sides combined must not exceed 4 metres in width. Where one side is already cleared 4 metres or more, up to 1 metre may be cleared on the other side.
Existing buildingsThe minimum extent needed to use or maintain a building built under a planning or building permit issued before 15 September 2008. It does not cover the operation or maintenance of a fence, or vegetation more than 10 metres from the outermost point of the building.
Personal useReasonable amounts of wood for the owner or lawful occupier, for uses such as heating, cooking, building and fence construction, and hobbies such as arts and craft. It does not cover contiguous land under 10 hectares, removal by means other than cutting or chopping, or a standing native tree of 40 centimetres trunk diameter or more, dead trees included.
Planted vegetationNative vegetation that was planted or grown from direct seeding. It does not cover vegetation planted or managed with public funding for land protection or biodiversity, unless the funding agency gave written permission.
RegrowthNative vegetation that has regenerated on land lawfully cleared of naturally established native vegetation and is under 10 years old. Bracken is also listed. The exemption does not apply where flood, fire or another natural disaster destroyed or damaged the vegetation.
Fire protectionThe minimum extent for fire fighting, planned burning, and fuelbreaks or fire access tracks up to a combined width of 6 metres. Work under a fire prevention notice and clearance around electric lines under the Electricity Safety Act 1998 code are also listed. The clause points to clause 52.48 for more bushfire exemptions.

New South Wales: two systems on the state page

The NSW Department of Climate Change, Energy, the Environment and Water names the Land Management and Biodiversity Conservation Framework as the structure for clearing native vegetation. Legislation under it is administered by the department, Local Land Services and the NSW Biodiversity Conservation Trust.

The department's page splits clearing in two. On rural land it is legislated by the Local Land Services Act 2013, administered by Local Land Services. The department builds the native vegetation regulatory mapping and handles compliance under that Act.

In urban areas and on land zoned for environmental protection, clearing falls under the State Environmental Planning Policy (Biodiversity and Conservation) 2021, formerly the Vegetation in Non-Rural Areas policy of 2017. Local councils administer it, and it lets them manage clearing in their area through a permit system. The Biodiversity Offsets Scheme is the offsetting framework for development impacts.

Queensland: the vegetation management framework

The Queensland Government regulates clearing through the vegetation management framework. The framework consists of the Vegetation Management Act 1999, the Planning Act 2016, their regulations, policies and codes, and the State Policy for Vegetation Management.

The state defines clearing as removing, cutting down, ringbarking, pushing over, poisoning, or destroying vegetation in any way, including by burning, flooding or draining. Clearing does not include destruction of standing vegetation by stock, or lopping a tree. Lopping means cutting or pruning branches without removing the trunk and without cutting so severely that the tree is likely to die. Vegetation means a native tree or plant other than grass or non-woody herbage, a plant in a grassland regional ecosystem, or a mangrove.

The framework allows clearing of remnant vegetation and regulated regrowth vegetation where it is for low-risk exempt purposes, is done under an accepted development vegetation clearing code, or serves a relevant purpose listed in the Act. Remnant and regulated regrowth vegetation can be cleared only under an assessment category. The category depends on the purpose of the clearing, the land tenure and what the vegetation is mapped as.

Queensland assessment categories
CategoryWhat the state says
Exempt clearing workRoutine property management activities. There is no requirement to notify the state or apply for approval.
Accepted development vegetation clearing codesCodes cover low-risk activities such as fodder harvesting and weed control. The user notifies the state before starting, then follows the code.
Area management plansNormally used for issues a code does not address, and for a regional approach to an activity such as weed control. The user notifies the state before starting, then follows the plan.
Development approvalsA regulatory approval obtained before development starts, sought by lodging a development application. The framework allows applications only for certain purposes.

The state offers free online property reports and vegetation maps that show how the vegetation on a property is mapped.

Sources