Wildfire plans and tree clearing in New Mexico: the regulator and the utility plan

New Mexico's Public Regulation Commission does not require a utility wildfire mitigation plan. Public Service Company of New Mexico files one anyway, and its 2026 plan sets out its tree pruning, patrols and clearing.

Checked against the sources at the bottom of this page on October 16, 2026. Rules, fees and pay change: the source has the last word.

This page reports what the official source says. It is not legal advice: ask the office named here. The facts here come from three documents. They are Public Service Company of New Mexico's (PNM) Wildfire Mitigation Plan 2025, its Wildfire Mitigation Plan 2026 filed with the New Mexico Public Regulation Commission (NMPRC) on April 1, 2026, and the company's wildfire safety page. Other regions appear in the guide to utility wildfire plans and tree clearing.

The regulator and the filing

The NMPRC's home page puts its aim as safe operations and reliable utility services at fair, just and reasonable rates. PNM's 2025 plan says the Commission does not require a wildfire mitigation plan to be filed. The same plan says PNM filed its first one with the Commission in 2021 and has revised it every year since.

The 2026 plan went in on April 1, 2026, through the Commission's PRCe360 e-filing system. Its cover letter is addressed to the Records Bureau Chief and filed in Case No. 22-00154-UT. The case caption reads "In the matter of an inquiry into electric public utilities' vegetation management plans and procedures". The plan carries a document approval signed March 31, 2026, by the company's Senior Vice President for New Mexico operations.

A second attachment, the Public Safety Power Shutoff plan, is filed separately under rule 17.9.560.15(F) of the New Mexico Administrative Code. That rule requires utilities to review curtailment plans periodically and file public summary versions with the Commission for information. The 2026 plan says it is reviewed and revised every year before March.

Vegetation management in the plan

Section 4.2 of the 2026 plan describes PNM's vegetation management program. It says the program is meant to comply with Section 218 of the National Electrical Safety Code and, where applicable, the North American Electric Reliability Corporation's Reliability Standard FAC-003-5. An Associate Director of Vegetation Management and Wildfire Risk oversees it. A manager and a team of specialists supervise the contracted tree crews that prune and clear near the lines.

The plan names the American National Standards Institute A300 standard for pruning and describes natural directional pruning, which steers regrowth away from the lines. Clearances depend on species, and the target is to prune trees for three years of clearance.

Line typePatrol and clearing
Transmission rated above 200 kVPatrolled every year, with no more than 18 months between patrols. Crews keep clearances and control incompatible vegetation, meaning plants that at full height would reach the minimum clearance distance from the conductor
Transmission rated below 200 kVPatrolled every other year or as needed, with a focus on fast-growing areas near water. Work follows patrols, tree-related outages, remote sensing, work requests and field observations
Distribution inside high fire risk areasWork is scheduled at the start of each year from inspection findings, past vegetation-related outages and customer input. Three-phase, single-phase and open-wire secondary lines are all included

In 2018, PNM completed a five-year project that cleared incompatible species along the full legal width of the right-of-way on required facilities, nearly 1,100 miles of transmission line. Edge pruning and clearing of incompatible species use Integrated Vegetation Management, which the plan defines as promoting native, low-growing plant communities with chemical, biological, cultural, mechanical or manual treatments.

Remote sensing, tree risk and contractor duties

PNM reports using LiDAR, high-resolution imagery and satellite imagery with artificial intelligence analysis on nearly all of its transmission and distribution lines inside the high fire risk areas. The plan says the satellite analysis is collected every year and used to classify vegetation distance from PNM facilities and to identify hazard trees. Enhanced inspections and clearing may follow.

The plan also describes a Utility Tree Risk Assessment process. It aims at any tree tall enough to strike supply lines if it failed. The plan calls the Level 1 Limited Visual Assessment the most common level in utility work, done on foot, by vehicle or by aerial patrol, and recorded by circuit or line segment instead of by tree.

PNM requires its contracted tree crews to run a wildfire prevention program. The plan lists annual training for all employees and firefighting tools on every truck at each job site. PNM specialists visit the work to check compliance, and the company's Red Flag Warning communication protocol includes the contractors. On days when fuel moisture, temperature, humidity and wind create what the plan calls an unacceptable risk, field staff modify or halt activities.

Where the work falls and what it cost

The plan's text counts 11 high fire risk areas. Its location table gives the area of each in square miles, including Santa Fe (961), Silver City (2,867), Fort Sumner (819) and Ruidoso (312). Silver City reads 2,824 in an earlier table of the same plan. PNM states that it prioritized these areas in 2025 and also did vegetation work outside them. The 2026 plan's cost table gives these figures for the work it counts as incremental wildfire mitigation:

  • Additional transmission vegetation: US$307,198 in 2024 and US$554,422 in 2025.
  • Additional distribution vegetation in high fire risk areas: US$2,799,167 in 2024 and US$3,009,030 in 2025.
  • Cyclical vegetation management program: it did not exist in 2024, and cost US$1,133,503 in 2025.
  • Total: US$3,106,365 in 2024 and US$4,696,955 in 2025.

The company's wildfire safety page tells the public that vegetation touching power lines can cause outages or a spark. It also says residents of a high fire risk area will likely experience Wildfire Safety Mode or a Public Safety Power Shutoff.

Sources