ArbNation Join free

Arboricultural method statement: what goes in it and when a council asks for one

A method statement sets out how trees on a building site are protected while the work goes on. Bassetlaw lists its contents, the London Tree Officers Association drafts the condition that calls for it, and BS 5837 is the yardstick.

Checked against the sources at the bottom of this page on October 16, 2026. Rules, fees and pay change: the source has the last word.

An arboricultural method statement, called an AMS, is the document that turns a tree protection plan into site procedure. UK councils ask for it with a planning application or attach it as a condition. Bassetlaw District Council, Leeds City Council, Slough Borough Council and the London Tree Officers Association (LTOA) each describe it.

What a council means by an AMS

Bassetlaw describes an AMS as the measures to be carried out so that adequate tree protection is in place during construction. It lists what a method statement would normally include:

  • timing and phasing of all tree works tied to the development
  • carrying out, monitoring, supervising and maintaining the tree protection measures
  • the same for pre-development tree works
  • the same for any approved activity inside the root protection area of a retained tree
  • depth and type of foundation near retained and planted trees
  • monitoring to confirm that every tree condition is met

The Arboricultural Association's 2024 workshop on the draft BS 5837 revision defines it more widely. In the draft, an AMS is the method for monitoring, carrying out, supervising and reporting any part of a development that is within the root protection area, or could lose or damage a retained feature.

When a council asks for one

Bassetlaw states that an AMS may be required as a planning condition for any application involving development near trees that are to be kept. It adds that too little information on trees may lead to the application being regarded as invalid.

Slough lists the AMS among the documents for any application with trees within the site or on its edge, householder applications included. Leeds uses BS 5837 Table B.1: the heads of terms of an AMS go in with the planning application, and a detailed AMS comes at reserved matters or planning conditions.

Triggers named in the LTOA condition

The LTOA's suggested standard wording for planning conditions includes a tree protection condition. It calls for a scheme, including a tree protection plan and an AMS in line with BS 5837:2012, to be approved before the development begins, demolition included. The matters the plan and statement must settle include:

  • location and installation of services, utilities and drainage
  • demolition and construction inside the root protection area
  • roads, parking areas and driveways built to a no-dig specification, with sections and levels
  • protective fencing, scaffolding and ground protection
  • site access, temporary parking, welfare facilities, storage, concrete mixing and fires
  • root pruning, supervision by a suitably qualified tree specialist and reporting of inspections

The LTOA pairs it with separate conditions for a pre-commencement site meeting, for arboricultural supervision and for a completed supervision schedule sent to the council within 28 days of completion. These conditions are set out in the guide to planning conditions on trees.

What it is checked against

Bassetlaw points to the full guidance on the survey information, protection plan and method statement in BS 5837, the 2012 edition. Slough requires the reports to comply with BS 5837:2012. Its scope and edition are in the outline of BS 5837.

Sources