Dielectric testing of insulated aerial devices: OSHA 1910.67, 1910.269 and the ANSI A92.2 test reference

OSHA 1910.67 sends electrical tests on aerial lifts to section 5 of ANSI A92.2-1969 and prints no interval. 1910.269 sets a daily boom-current test with a leakage limit of 1 microampere per kilovolt.

Checked against the sources at the bottom of this page on October 16, 2026. Rules, fees and pay change: the source has the last word.

The facts on this page come from the named regulators and standards bodies. It is not training and does not teach the work. The texts are 29 CFR 1910.67 on vehicle-mounted work platforms, 29 CFR 1910.269 on electric power generation, transmission and distribution, and two OSHA letters of interpretation on ANSI A92.2.

1910.67: electrical tests and the insulated portion

Paragraph 1910.67(a)(5) defines an insulated aerial device as an aerial device designed for work on energized lines and apparatus. Paragraph (c)(3), titled Electrical tests, says electrical tests shall be made in conformance with section 5 of ANSI A92.2-1969. It allows equivalent DC voltage tests in place of the AC voltage test in A92.2-1969, where the equipment maker or an equivalent entity approves the DC test.

The OSHA text does not print a test interval, a test voltage or a pass mark.

Two other 1910.67 items touch the insulation. The insulated portion of an aerial lift shall not be altered in any manner that might reduce its insulating value, under (c)(2)(xi). Lift controls shall be tested each day before use, under (c)(2)(i). Aerial lifts acquired on or after July 1, 1975 are tied to ANSI A92.2-1969 by (b)(1).

1910.269: boom-current test and insulated aerial lifts

Paragraph 1910.269(q)(3), on live-line barehand work, carries the boom-current test in (q)(3)(xiii). The employer has employees perform the test before starting work each day, each time during the day when they meet a higher voltage, and when changed conditions point to a need for another test.

Item1910.269(q)(3)(xiii)
WhenBefore work each day, at each higher voltage met during the day, and when conditions change
MethodThe bucket is placed in contact with an energized source equal to the voltage to be met, for at least 3 minutes
LimitLeakage current may not exceed 1 microampere per kilovolt of nominal phase-to-ground voltage
On a faultWork from the aerial lift is suspended immediately on any sign of a malfunction

Paragraph (q)(3)(ix) says aerial lifts for live-line barehand work have dual controls, upper and lower. The word dielectric does not appear in the text of 1910.269(p) or (q) about aerial lifts. The only uses are in definitions, in the test for positioning straps and in the appendices.

Paragraph 1910.269(p)(4)(i) requires mechanical equipment to keep the employer's minimum approach distances from exposed energized lines. The insulated portion of an aerial lift, operated by a qualified employee in the lift, is exempt if the minimum approach distance is kept between the uninsulated portions of the lift and objects at a different potential. Paragraph (p)(4)(iii)(B) lets equipment be insulated for the voltage involved, positioned so its uninsulated parts stay outside the minimum approach distances.

Letters of interpretation on A92.2 editions

A November 8, 2005 OSHA letter covers 29 CFR 1926.453(a)(1), the construction rule. It says aerial devices that meet ANSI A92.2-1979 or the 1990 edition need not also meet section 4.1 of the 1969 edition, because OSHA found those editions equivalent in the Subpart L rulemaking. Section 4.1 of the 2001 edition is identical to the 1990 text. The letter says questions about 1910.67(b)(1) go to the Directorate of Enforcement Programs.

A May 5, 1997 OSHA letter covers a digger derrick that is also used as an aerial lift. It says 1910.67 and 1926.453 apply when the machine is used as an aerial lift and require the applicable parts of ANSI A92.2-1969. Using a current consensus standard in place of the earlier cited revision is treated as a de minimis violation, with no citation or penalty, if the current revision gives at least the same protection.

The same letter was asked whether the lift could work energized transmission lines on a 7,200 volt phase in a 12,470 volt wye system if 1910.67 is met. The answer was no: 1910.269, including the mechanical equipment rules in paragraph (p), applies when employees work on or near exposed power transmission and distribution conductors.

Both letters state that interpretation letters explain the requirements and cannot create additional employer obligations.