Pick weight terms: what a crane operator needs a tree crew to state
OSHA's crane rules tie a pick to four figures: the load weight, the rigging counted in it, the radius and the rated capacity. Britain's LOLER requires every lifting operation to be planned by a competent person.
Checked against the sources at the bottom of this page on October 19, 2026. Rules, fees and pay change: the source has the last word.
The named codes and standards are described here as published. It is not training and does not teach the work.
The terms in one table
| Term | Wording in the named source |
|---|---|
| Load | OSHA 1926.1401: the object or objects hoisted, or their weight, together with the load-attaching equipment such as the load block, ropes, slings, shackles and other ancillary attachments |
| Rated capacity | OSHA 1926.1401: the maximum working load the manufacturer permits under specified working conditions, such as equipment configuration, radii and boom length |
| Radius | OSHA 1926.1431: rated capacity is read "for the radius and configuration of the equipment". OSHA 1926.1401 defines a load moment indicator as sensing the overturning moment, which is load multiplied by radius |
| Fall zone | OSHA 1926.1401: the area, including but not limited to the area directly beneath the load, where it is reasonably foreseeable that suspended material could fall in an accident |
| Lifting operation | LOLER regulation 8(2): an operation concerned with the lifting or lowering of a load |
| Competent person | OSHA 1926.1401: someone able to identify existing and predictable hazards who has authority to take prompt corrective measures |
Load weight in the OSHA operation rule
Section 1926.1417(o) bars operating equipment beyond its rated capacity. It also bars requiring an operator to do so. The operator confirms that the load is within rated capacity by at least one of two methods.
The first method is a weight from a source the industry recognises, such as the load's manufacturer, or from a recognised calculation. One example in the rule is a steel beam worked out from measured dimensions and a known weight per foot. The rule adds that this information must be provided to the operator before the lift when the operator asks for it.
The second method is to begin hoisting and read a load weighing device, load moment indicator, rated capacity indicator or rated capacity limiter. If the load exceeds 75 percent of the maximum rated capacity at the longest radius that will be used in the lift, the operator does not proceed until the weight is confirmed by the first method.
Rigging counted in the load
The OSHA definition of load includes the load block, ropes, slings and shackles, so the rigging is part of the figure. Section 1926.1431 repeats this for hoisting personnel. A suspended personnel platform's total load, with the hook, load line and rigging, is capped at 50 percent of rated capacity for the radius and configuration of the equipment. For hoisting personnel without a platform, the cap covers the hook, load line, rigging and any other equipment that imposes a load.
The same section sets a strength figure for the rigging hardware. Wire rope, shackles, rings, master links and other hardware, and hooks, must support at least five times the maximum intended load applied to that component. Where rotation resistant rope is used, the slings must support at least ten times.
Other operating terms in section 1926.1417
- Load charts and rated capacities must be readily available in the cab at all times.
- The competent person adjusts the equipment or operations for the effect of wind, ice and snow on stability and rated capacity.
- The operator tests the brakes on each load that is 90 percent or more of the maximum line pull, by lifting a few inches and applying them.
- A tag or restraint line is used if needed to stop hazardous rotation of the load.
- The operator obeys a stop or emergency stop signal from anyone.
- The equipment is not used to drag or pull loads sideways.
Planning in Britain
LOLER regulation 8 puts a duty on every employer: each lifting operation involving lifting equipment is properly planned by a competent person, appropriately supervised and carried out in a safe manner. The HSE groups its LOLER guidance under headings that include safe lifting by machine, planning and organising lifting operations, and lifting people. The regulation prints no list of terms, and the HSE overview page prints none either. The terms in the table above are OSHA's.
The standard behind the cranes
ASME's scope page for B30.5 says the standard addresses crawler cranes, locomotive cranes and wheel-mounted cranes that run on internal combustion engines or electric motors. It excludes side boom tractors, digger derricks, knuckle boom and trolley boom cranes, and cranes with a maximum rated capacity of one ton or less. The page covers the construction, inspection, testing, maintenance and operation of the cranes it names. The clause text is sold.
The site's pages on lift plans in HSE guidance and cranes and lifting words cover the wider vocabulary.
Sources
- OSHA, 29 CFR 1926.1417 Operation (eCFR), read October 19, 2026
- OSHA, 29 CFR 1926.1431 Hoisting personnel (eCFR), read October 19, 2026
- OSHA, 29 CFR 1926.1401 Definitions (eCFR), read October 19, 2026
- Lifting Operations and Lifting Equipment Regulations 1998, regulation 8, legislation.gov.uk, read October 19, 2026
- HSE, Lifting Operations and Lifting Equipment Regulations (LOLER), page updated March 16, 2023, read October 19, 2026
- ASME, B30.5 Mobile and Locomotive Cranes, scope page, read October 19, 2026