This page shows one public bid tabulation as the city published it. These are government contract prices on one sheet, not market quotes and not advice. The bidders are shown as Bidder A, Bidder B, Bidder C and Bidder D in the order the sheet lists them. The sheet itself names the firms and is linked below. The wider picture is on the public tree contract bids page.
The contract
| Fact | What the sheet says |
| Agency | City of Yakima, Washington, for streets and parks |
| Project number | 22533 |
| Work | Tree trimming, pruning and removal services |
| Sheet title | Quote tabulation and comparison sheet |
| Quotes opened | June 20, 2025 at 2:00 p.m. |
| Contract term | 5 years, August 5, 2025 to August 4, 2030 |
| Digital signature stamps | June 30, 2025 and July 1, 2025 |
| Bidders on the sheet | 4 |
| Award recommendation printed | Schedule 1 regular rates to one firm, and schedule 1 emergency rates and schedule 2 stump grinding to another, as the lowest responsive bid from a responsible bidder for each schedule. Schedules 3 and 4 are used as needed from each awarded contractor |
| Tax | A Sales tax line (WSST) below the sub-total, labelled 8.3 percent |
What the sheet shows about the lines
The sheet prices crew time, not trees. Schedule 1 has hour and day rates for a two-person crew with equipment, and for each additional crew person, once as regular rates and once as emergency rates. Schedule 2 has the same four rates for stump grinding. Schedule 3 prices travel by the mile outside the city limits for a boom truck and a regular truck, in addition to the regular rates. Schedule 4 prices traffic control by the hour, and the sheet says those unit prices apply only for additions or deletions to the traffic control work and that the city can reject any of them.
Every line has a quantity of 1. So each printed sub-total is the plain sum of the unit prices in its column and is not an estimate of what the city will spend. The sheet adds the five schedule sub-totals, then the sales tax line, to reach a grand total base bid. That total is a comparison device, and the contract itself is for hourly and daily rates over five years. The tax line printed for Bidder D is 8.2 percent of its sub-total, where the other three lines are 8.3 percent of theirs. The page shows the numbers as printed.
Prices as printed
Each bidder wrote one unit price per line. Where the sheet shows a total beside a unit price, it is the same number because the quantity is 1.
Schedule 1, regular rates
| Line and item | Bidder A | Bidder B |
| 1. Trimming, pruning or removal, two-person crew with equipment, per hour | US$260.00 | US$248.00 |
| 2. Same crew, per day (based on an 8 hour work day) | US$2,080.00 | US$1,984.00 |
| 3. Each extra crew person with equipment, per hour | US$75.00 | US$78.00 |
| 4. Each extra crew person with equipment, per day | US$600.00 | US$624.00 |
| Sheet sub-total, schedule 1 regular | US$3,015.00 | US$2,934.00 |
| Line and item | Bidder C | Bidder D |
| 1. Trimming, pruning or removal, two-person crew with equipment, per hour | US$300.00 | US$220.00 |
| 2. Same crew, per day (based on an 8 hour work day) | US$2,400.00 | US$1,760.00 |
| 3. Each extra crew person with equipment, per hour | US$95.00 | US$95.00 |
| 4. Each extra crew person with equipment, per day | US$760.00 | US$760.00 |
| Sheet sub-total, schedule 1 regular | US$3,555.00 | US$2,835.00 |
Schedule 1, emergency rates
| Line and item | Bidder A | Bidder B |
| 5. Trimming, pruning or removal, two-person crew with equipment, per hour | US$260.00 | US$248.00 |
| 6. Same crew, per day (based on an 8 hour work day) | US$2,080.00 | US$1,984.00 |
| 7. Each extra crew person with equipment, per hour | US$75.00 | US$78.00 |
| 8. Each extra crew person with equipment, per day | US$600.00 | US$624.00 |
| Sheet sub-total, schedule 1 emergency | US$3,015.00 | US$2,934.00 |
| Line and item | Bidder C | Bidder D |
| 5. Trimming, pruning or removal, two-person crew with equipment, per hour | US$375.00 | US$320.00 |
| 6. Same crew, per day (based on an 8 hour work day) | US$3,000.00 | US$2,560.00 |
| 7. Each extra crew person with equipment, per hour | US$125.00 | US$95.00 |
| 8. Each extra crew person with equipment, per day | US$1,000.00 | US$760.00 |
| Sheet sub-total, schedule 1 emergency | US$4,500.00 | US$3,735.00 |
Schedule 2, stump grinding, regular rates
| Line and item | Bidder A | Bidder B |
| 9. Stump grinding, two-person crew with equipment, per hour | US$190.00 | US$160.00 |
| 10. Same crew, per day (based on an 8 hour day) | US$1,520.00 | US$1,280.00 |
| 11. Each extra crew person with equipment, per hour | US$75.00 | US$80.00 |
| 12. Each extra crew person with equipment, per day | US$600.00 | US$640.00 |
| Sheet sub-total, schedule 2 | US$2,385.00 | US$2,160.00 |
| Line and item | Bidder C | Bidder D |
| 9. Stump grinding, two-person crew with equipment, per hour | US$225.00 | US$195.00 |
| 10. Same crew, per day (based on an 8 hour day) | US$1,800.00 | US$1,560.00 |
| 11. Each extra crew person with equipment, per hour | US$100.00 | US$95.00 |
| 12. Each extra crew person with equipment, per day | US$800.00 | US$760.00 |
| Sheet sub-total, schedule 2 | US$2,925.00 | US$2,610.00 |
Schedule 3, outside city limits, travel in addition to regular rates
| Line and item | Bidder A | Bidder B |
| 13. Boom truck, per mile | US$0.00 | US$0.00 |
| 14. Regular truck, per mile | US$0.00 | US$0.00 |
| Sheet sub-total, schedule 3 | US$0.00 | US$0.00 |
| Line and item | Bidder C | Bidder D |
| 13. Boom truck, per mile | US$0.35 | US$0.00 |
| 14. Regular truck, per mile | US$0.35 | US$0.00 |
| Sheet sub-total, schedule 3 | US$0.70 | US$0.00 |
Schedule 4, traffic control (prices used only for additions or deletions)
| Line and item | Bidder A | Bidder B |
| 15. Traffic control, sidewalk closure, per hour | US$45.00 | US$28.00 |
| 16. Traffic control, non-arterial street closure, per hour | US$45.00 | US$60.00 |
| 17. Traffic control, arterial street closure, per hour | US$45.00 | US$116.00 |
| Sheet sub-total, schedule 4 | US$135.00 | US$204.00 |
| Line and item | Bidder C | Bidder D |
| 15. Traffic control, sidewalk closure, per hour | US$150.00 | US$150.00 |
| 16. Traffic control, non-arterial street closure, per hour | US$150.00 | US$150.00 |
| 17. Traffic control, arterial street closure, per hour | US$150.00 | US$150.00 |
| Sheet sub-total, schedule 4 | US$450.00 | US$450.00 |
Totals as printed
| Line | Bidder A | Bidder B |
| Sub-total of the five schedules | US$8,550.00 | US$8,232.00 |
| Sales tax line (WSST) | US$709.65 | US$683.26 |
| Grand total base bid | US$9,259.65 | US$8,915.26 |
| Discount or terms printed | 5 percent, net 10 days | 0 percent, net 0 days |
| Line | Bidder C | Bidder D |
| Sub-total of the five schedules | US$11,430.70 | US$9,630.00 |
| Sales tax line (WSST) | US$948.75 | US$789.66 |
| Grand total base bid | US$12,379.45 | US$10,419.66 |
| Discount or terms printed | None listed | 0 percent, net 0 days |
Where to read the sheet
The city links the sheet from its list of final bid results, under project 22533. The city purchasing page explains the process. Both are in the sources below.
Sources
- City of Yakima, quote tabulation and comparison sheet for project 22533, tree trimming, pruning and removal, read October 9, 2026
- City of Yakima, final bid results page, read October 9, 2026
- City of Yakima, purchasing page, read October 9, 2026