Rigging plans and lift planning checklists: the planning points the codes list
Five published sources list what is planned before a rigging job: the LOLER duty in Great Britain, the Arboricultural Association's code and rigging checklist, New Zealand's approved code and the SafeWork NSW code. None of them is a safe system of work.
Checked against the sources at the bottom of this page on October 19, 2026. Rules, fees and pay change: the source has the last word.
The named codes and training bodies are described here as published. It is not training and does not teach the work. The Arboricultural Association calls its rigging checklist a set of notes on good practice that are not compulsory and not a substitute for adequate training. The lists below are the sources' own planning points, grouped by source.
Great Britain: LOLER regulation 8
Regulation 8 of the Lifting Operations and Lifting Equipment Regulations 1998 covers the organisation of lifting operations. Every lifting operation involving lifting equipment must be properly planned by a competent person, appropriately supervised and carried out in a safe manner. The regulation defines a lifting operation as an operation concerned with the lifting or lowering of a load. The regulations apply in Great Britain.
Arboricultural Association, Tree Work at Height code
The industry code of practice, second edition, May 2020, says all tree work operations at height must be planned by a competent person with enough proficiency to plan, assess and resource the work. The decision to work at height must be justified, and work at height is to be avoided where reasonably practicable. The code lists six things that are in place before aerial tree work starts.
- An assessment of whether tree work at height is appropriate, based on a pre-work evaluation.
- Safe systems of work that define the methods.
- Adequately trained and proficient operators.
- A point-of-work, site-specific risk assessment.
- Emergency planning, including resources for aerial rescue, first aid or evacuation.
- A plan, communicated to the crew, that covers the first five.
The code splits the roles into a responsible person such as the employer, a competent person such as a supervisor or team leader, and a proficient operator such as a climbing arborist. For rigging, it lists what operators must be able to do. They identify drop zones, estimate log and crown section mass, and calculate expected peak forces. They select compatible components for the rigging system, understand strength loss from knots in cordage, and use accurate cutting techniques. Where a crane is involved, operators agree and communicate a sequence of work, assess the weight of sections, assess balance and likely pivot, and communicate with the crane supervisor, operator and ground staff.
Arboricultural Association, Safety Guide 3
Safety Guide 3, Rigging and Dismantling, is dated December 2021 and is summarised from Technical Guide 3. Its section 3.0, Planning Rigging Operations, is a nine-line checklist with Yes, No and N/A boxes.
| Line | Planning question in the guide |
|---|---|
| 3.a | Do the proficient operators on site know who the competent person is? |
| 3.b | Is there a suitable and sufficient site-specific risk assessment? |
| 3.c | Has the risk assessment been communicated and agreed by all parties? |
| 3.d | Do operators have defined roles and responsibilities, and do they understand them? |
| 3.e | Has an aerial rescue plan been agreed? |
| 3.f | Do operators have the level of proficiency for their tasks? |
| 3.g | Do operators know what to do if they have concerns about unsafe work practices? |
| 3.h | Have drop, work and exclusion zones been identified, and do all operators know them? |
| 3.i | Has an adequate tree condition assessment been carried out? |
The guide's other headed sections are rigging techniques, anchor forces, operator positioning, system components, working loads, compatibility and configuration, knots and slings, strength loss, weight of sections, anchor selection, peak loads, and inspection and maintenance. Section 8 asks for the safe working load of the equipment, whether it is adequate for the intended load, and the safety factor used. Section 15 asks about pre-use checks, thorough examination and examination records.
New Zealand approved code of practice
The code of practice for safety and health in arboriculture, November 2012, lists what planning for a tree removal takes into account. The items are the surrounding area including other trees, the species, shape and condition of the tree, its lean, broken branches and deadwood, and wind force and direction. They also include decayed or weak spots, the location of other persons, property and utilities and the means to protect them, and the size and terrain of the work area. When branches are removed before the tree comes down, the arborist tries to determine whether the tree can withstand the strain of the lowering procedures. If not, other means of removal are to be considered.
The code also requires working techniques and work progression to be fully discussed and understood by ground staff before climbing starts. Rescue procedures are outlined and understood. In its section on winches, wire ropes and accessories, the safe working load is one-sixth of the breaking strength for all arboricultural operations. Strops that anchor pulling blocks are at least 1.5 times the safe working load of the pulling rope.
SafeWork NSW Tree works code
The SafeWork NSW code of practice, March 2026, says planning includes identifying hazards, assessing risks and putting controls in place. It lists seven considerations. They are a visual inspection of the trees to set the scope of work, access methods and weather. They also include exclusion and drop zones, selecting workers and equipment, and a safe system of work with planning for emergencies and first aid. The seventh is the location of overhead electric lines and underground services. A competent person inspects and assesses the tree, looking at its condition and structural integrity, faults such as decay, hollows and root plate failure, wind loading and ground conditions.
Under the same code a person conducting a business or undertaking must see that an emergency plan is prepared for the work site. Where workers are at height, a rescue plan must be in place. It includes a way to reach and lower the climber, emergency contact details, a crew member trained in aerial rescue, and dedicated rescue equipment. The code is published under the Creative Commons Attribution 4.0 licence.
Sources
- legislation.gov.uk, The Lifting Operations and Lifting Equipment Regulations 1998, SI 1998 No. 2307, read October 19, 2026
- Arboricultural Association, Industry Code of Practice for Arboriculture: Tree Work at Height, second edition, May 2020, read October 19, 2026
- Arboricultural Association, Safety Guide 3: Rigging and Dismantling, December 2021, read October 19, 2026
- WorkSafe New Zealand, Approved Code of Practice for Safety and Health in Arboriculture, November 2012, read October 19, 2026
- SafeWork NSW, Tree works code of practice, March 2026 (CC BY 4.0), read October 19, 2026