Tree pit designs for streets: open pits, trenches, continuous soil and grates

Surrey County Council sets a 1 m square minimum open pit and avoids grilles. Denver guidelines prefer a 4-inch curb with no grate and 750 to 1000 cubic feet of uncompacted soil per tree.

Checked against the sources at the bottom of this page on October 16, 2026. Rules, fees and pay change: the source has the last word.

Open pits

Surrey County Council's Healthy Streets guidance, section 7.6, covers pits in hard surfaces. The surface opening is as large as the space allows and no smaller than 1 m square. The pit stays open, with layers of ground cover planting, and is not surfaced with paving. It starts with organic mulch 50 to 75 mm deep. Permanent ground cover follows once the tree is established. On busy streets the council names dense native planting, shrubs included, to stop litter collecting and deter verge parking.

Surrey states that tree grilles should be avoided because they collect rubbish. Where hard surfacing is required, it names permeable resin bound gravel, self-binding gravel or rubber crumb.

Grates and what the cities attach to them

The Denver Ultra-Urban Green Infrastructure Guidelines, fact sheet 8, give a 4-inch curb with no grate as the preferred treatment. The soil stays visible and is protected from compaction. City staff there have observed that trees surrounded by other vegetation are watered more often by nearby residents, and that grates can damage a tree when poorly maintained.

Where Denver does use a grate, it keeps at least 4 inches between grate and trunk, calls for easy maintenance, and inspects annually. The other option is permeable interlocking concrete pavement over the trench, brought to within 6 to 12 inches of the trunk. The Merri-bek City Council note for raingarden tree pits in Victoria, Australia, asks for lightweight, hinged grates that can be lifted by hand.

Trenches and continuous soil

Denver defines a tree trench as a bioretention facility in the amenity zone between street and sidewalk, and calls a trench with a single tree a tree pit. Trees are usually located 4 to 6 feet from the back of curb. The excavation is about 9 feet wide, and each planting area is at least 5 feet wide. A section holds up to three trees over roughly 66 to 86 feet, with an inlet and water control structure for every three trees. The guidelines ask for 750 to 1000 cubic feet of uncompacted rooting volume per tree.

Surrey ties pits, verges and trenches together to maximise root volume. With a structural solution, a trench can extend under paving, for example linking pits between parking spaces. Surrey says a medium tree usually requires 12 m3 of soil to establish fully. The council lists structural soil systems, crate and root cell systems, and raft systems for paved areas, and refers readers to Trees in Hard Landscapes (TDAG, 2014). Merri-bek notes that soil under pavements is compacted to carry traffic loads, which inhibits root growth, and that structural soils can supply water, nutrients and oxygen while the surface still carries those loads.

Pits that take street runoff

ItemWhat the manual prints
Merri-bek C120.08 (October 2022)Raingarden tree pit behind the kerb, with a tree as the only vegetation. Filter area usually 2 percent of the upstream impervious catchment
Merri-bek drainageFlushing point on the drainage pipe and a wide kerb inlet. Without an underdrain connection to stormwater, species tolerant of periodic waterlogging
Denver fact sheet 8Runoff enters through a curb opening, passes a fine-gravel filter, drains to an underdrain, and fills pore space around the roots
Denver sizingThree trenches of three trees each treat a block 400 feet long and 30 to 34 feet from street crown to right-of-way
Denver limitsTrenches suit streets that do not receive a deleterious amount of de-icing salt

Roots near buildings and services

Surrey adds that roots are contained and deflected from buildings and utilities by root barriers, and that root deflectors guide roots down at least 300 mm to protect paving layers. Merri-bek sets construction hold points: after drainage connections and before backfilling, and at practical completion.