Notice before utility tree work: the periods Missouri, Maryland and Indiana print

Missouri requires notice 7 to 90 days before planned utility tree work, Maryland 7 to 120 days, and Indiana at least two calendar weeks. Each rule also says who gets the notice and what it contains.

Checked against the sources at the bottom of this page on October 15, 2026. Rules, fees and pay change: the source has the last word.

This page reports what the official source says. It is not legal advice: ask the office named here. The rules are the Missouri Code of State Regulations, 20 CSR 4240-23, edition dated August 31, 2026, the Code of Maryland Regulations, COMAR 20.50.12.09, and the Indiana Utility Regulatory Commission's 170 IAC 4-9-4, from the Cornell Legal Information Institute mirror. Easement terms are covered in utility easements and trimming.

The three notice rules side by side

Notice windows for routine or planned utility vegetation work
StateRuleWindow
Missouri20 CSR 4240-23, section (7)At least 7 days, not more than 90 days, before the work
MarylandCOMAR 20.50.12.09, section DAt least 7 days, not more than 120 days, before cyclical planned work
Indiana170 IAC 4-9-4At least two calendar weeks before routine work

Missouri and Maryland also require written notice to a county and municipality contact at least 2 months ahead. Maryland lets a local government waive it. Indiana's section has no such step.

Missouri

The Missouri rule asks each electrical corporation for a diligent attempt to notify all affected property owners or occupants. The rule treats the duty as met when notice goes out between 7 and 90 days before the planned work. Notice goes by direct mailing, door hanger, postcard, bill insert, personal contact or another commission-approved method. The utility keeps a record of the dates, content and addresses of each notice until the next vegetation management cycle has been done for that owner or occupant.

The utility employs a vegetation manager. The manager's name and contact details go on the company website and on every notice the rule requires. The county and municipality notice must give planned dates and locations.

Maryland

COMAR 20.50.12.09 requires a reasonable attempt to notify the owner or occupant of every property where cyclical, planned work is to be done. Notice goes by direct mailing, door hanger, postcard, personal contact or another approved method, and not by bill insert alone. Each notice carries the contact details of a dedicated group customers can call. A utility that uses a call centre adopts a script or job aid written for vegetation calls.

For readily identified tree removals on residential properties, the utility contacts the customer or owner to discuss the removal before the work. It also offers direct communication with a vegetation management representative within 7 business days. Each utility reviews its vegetation complaints periodically to improve how it resolves them. Maryland's cyclical rules apply to the extent contract rights, property rights or other controlling law do not limit them.

Indiana

Rule 170 IAC 4-9-4 sets two calendar weeks. The notice is not required where the utility holds a written easement, government permit, contractual agreement or court order that expressly gives it the right to do the work, or in an emergency or storm event.

Written and in-person notices state that work is scheduled, explain what vegetation management is and why it is needed for safe and reliable service, give the estimated date, and give a telephone number. They also state that receipt starts the two-week window for calculating implied consent. A written notice carries the heading "TREE TRIMMING NOTICE", the mailing or delivery date, and the commission's website.

A customer can ask for the estimated day within three calendar days of the notice. The utility then gives it at least three business days before the work. An owner notified by newspaper has the same right.

Sources