ArbNation Join free

Utility vegetation management in New York: 16 NYCRR Part 84 and the Commission's right-of-way plans

New York's Public Service Commission rules in 16 NYCRR Part 84 cover transmission rights-of-way of 34 kV and above. Utilities file long-range plans, and aerial herbicide spraying needs a filing 60 days ahead.

Checked against the sources at the bottom of this page on October 16, 2026. Rules, fees and pay change: the source has the last word.

This page reports what the official source says. It is not legal advice: ask the office named here. The Department of Public Service (DPS) page on tree trimming and vegetation management and sections 84.1 and 84.2 of 16 NYCRR Part 84 set out the rules. They cover transmission rights-of-way, not the lines that run along streets to homes.

The framework for corridor plans

The DPS page says 16 NYCRR Part 84 and the Commission's order in Case 04-E-0822 set the framework for each utility's long-range vegetation management plan for its right-of-way corridors. Utilities must file plans covering transmission corridors of 34 kV and above, except where the lines lie entirely on public streets or roads. The requirements apply only to property the utility controls through fee or easement.

DPS describes corridor treatment as routine, on cycles that revisit each right-of-way periodically. During treatment, all tall-growing or undesirable vegetation is removed along the entire designed corridor. DPS staff review each utility's program every year. The review includes field inspections, analysis of tree-caused outages and trend analysis, with spending, staffing, acres treated, danger tree removal, herbicide use and complaints among the items. Herbicides used in corridors are approved by the federal Environmental Protection Agency and the state Department of Environmental Conservation. DPS prints no cycle length and no filing deadline.

NERC standard FAC-003, DPS adds, requires vegetation management planning for bulk transmission lines of 200 kV and above, and for lower-voltage lines deemed critical.

Section 84.2, the long-range plan

Section 84.2 required each New York Power Pool member system to submit a long-range right-of-way management plan by March 31, 1981. The Power Authority of the State of New York was excepted. The plan covers transmission facilities of 34 kV and above and goes to the Public Service Commission for review and approval. Lines located entirely on public streets or roads are excluded.

SubsectionWhat the plan describes
(a)The management structure, and the extent, voltage classes, widths and condition of the right-of-way system
(b)The functions of key right-of-way positions, including who sets long-range goals and annual objectives
(c)Past and present policies, the issues, and the goals set in response
(d)How landowners and land users are notified, how restrictions on chemical treatment are handled, and how treatments and cycles are set
(e)Mechanical, chemical and other techniques, with clearance standards, costs, effectiveness and environmental impact
(f)How annual maintenance plans are prepared, including crews, contractors, equipment, training and budgets
(g)Unresolved issues tied to current or planned research
(h)The regulations, licences and permits the work needs
(i)Funding levels for annual and multi-year goals
(j)How the plan is reviewed and revised, and the interval between revisions

Section 84.1, aerial spraying

A New York electric utility that wants to apply herbicide from the air to transmission right-of-way vegetation files a site-specific plan for each right-of-way. The plan has maps and charts, identifies the vegetation and the access conditions, explains how nearby water supplies and sensitive lands are protected, and shows how the spraying serves the utility's vegetation management goals. The filing comes at least 60 days before spraying is scheduled. Spraying cannot start until the filing requirements are met and the Commission approves the proposal. If the Commission has not acted within 45 days of filing, the plan is treated as approved.

Planting heights and complaints

The DPS page gives height guidelines for trees planted under a transmission right-of-way, measured from the center of the corridor.

Distance from centerTallest mature tree
30 to 60 feet15 feet
60 to 90 feet25 feet
90 to 120 feet60 feet

DPS says over 15,000 miles of electric transmission facilities run through New York, and over 90 percent of tree-caused transmission outages involved trees growing along or outside the right-of-way that fell into it. DPS says landowners should receive notice before utility work, with a name and phone number. It names Dig Safely New York at 811 or 1-800-962-7962, at least two and no more than 10 working days before digging to plant.

For a complaint, DPS says to contact the utility first, then the Public Service Commission Office of Consumer Services at 1-800-342-3377 or through the DPS website. The office answers from 8:30 a.m. to 4:00 p.m., Monday through Friday. The same steps apply to trimming or debris cleanup outside the right-of-way.