Aerial device pre-use checks and periodic examination: OSHA, LOLER and WorkSafe NZ

OSHA names one pre-use test for bucket truck controls, each day. LOLER sets a thorough examination every 6 months for equipment that lifts people. WorkSafe NZ guidance adds routine, six-monthly and major inspections with a logbook.

Checked against the sources at the bottom of this page on October 19, 2026. Rules, fees and pay change: the source has the last word.

The named regulators and guidance are described here as published. It is not training and does not teach the work.

Side by side

Pre-use checks, periodic examination and records
SourceBefore usePeriodic and records
US, OSHALift controls tested each day prior to use. Boom inspected before travel to see it is cradled and outriggers are stowed.Electrical tests to ANSI A92.2-1969, Section 5. No interval or record named.
Great Britain, LOLERNot set by the regulation. Inspection by a competent person between examinations, if appropriate.Thorough examination at least every 6 months for lifting persons, or under a scheme. Physical evidence of the last one goes with the equipment.
New Zealand, WorkSafeVisual inspection and functional test by the operator.Routine inspection at least every 3 months. Thorough examination at least every 6 months. Logbook and register kept with the machine.

United States

OSHA's aerial lift rule in general industry, 29 CFR 1910.67, and its construction twin, 1926.453, use near-identical wording for extensible and articulating boom platforms. Lift controls are tested each day prior to use to determine that they are in safe working condition. Only trained persons (1910.67) or authorized persons (1926.453) operate an aerial lift. Before the lift is moved for travel, the boom is inspected to see that it is properly cradled and the outriggers are stowed.

Both rules tie their electrical tests to Section 5 of ANSI A92.2-1969. They allow equivalent DC voltage tests that the maker or an equivalent entity approves. Critical hydraulic and pneumatic components must meet Section 4.9 of that standard on bursting safety factor. A lift field modified for other uses needs the modification certified in writing by the maker or an equivalent entity, such as a nationally recognized testing laboratory.

The rules name no periodic inspection interval and no record. Boom and basket load limits specified by the maker are not to be exceeded.

Great Britain

Regulation 9 of the Lifting Operations and Lifting Equipment Regulations 1998 puts the duty on the employer. Lifting equipment is thoroughly examined before first use unless it is new and comes with a declaration of conformity made not more than 12 months earlier. Where safety depends on installation, it is examined after installation and after assembly at a new site.

For equipment exposed to deterioration that could lead to dangerous situations, thorough examination comes at least every 6 months for equipment for lifting persons or an accessory for lifting. Other lifting equipment is examined at least every 12 months. An examination scheme can replace the fixed periods. An examination is also due each time exceptional circumstances liable to jeopardise safety have occurred.

If appropriate for the purpose, a competent person inspects the equipment at suitable intervals between thorough examinations. Equipment does not leave the employer's undertaking, or enter it from another, without physical evidence of the last thorough examination.

HSE publishes the Approved Code of Practice and guidance for these regulations as L113 (second edition, December 2014, amended 2018). HSE says L113 builds on the Provision and Use of Work Equipment Regulations and applies across every sector that uses lifting equipment.

New Zealand

The WorkSafe New Zealand MEWP guidelines of August 2014 set a layered regime. WorkSafe notes the guidance has not been updated for the Health and Safety at Work Act 2015.

  • Pre-operation check. The operator gives the machine a visual inspection and functional test before use. The listed items include the six-monthly certificate being current, platform and base controls, emergency controls and retrieval system, alarms, anchor points, leaks, brakes, tyres, outriggers, guardrails and the slew brake.
  • Routine inspection. Owner, hirer and supplier inspect at least every 3 months, and between hires for a hire machine. A competent person does it, and a written report follows.
  • Six-monthly inspection. A competent person thoroughly examines the machine after an accident, incident, or major repair or modification, or at least every 6 months. A certificate is attached near the ground controls or the platform entrance.
  • Electrical insulation. Insulated machines are tested at least every 6 months. A fibreglass boom has an acoustic emission test at least every 24 months.
  • Enhanced and major inspections. Critical parts are inspected and tested every 5 years. A machine in service for 10 years needs a major inspection unless it has had an enhanced one. An imported or re-commissioned machine without continuous records needs one too.

The logbook records pre-operation and routine inspections and maintenance. The owner keeps at least the last 14 days of daily pre-operation reports, or those since the last routine inspection, plus summaries of the last routine, major and six-monthly inspections and the repairs made.

Maintenance follows the maker's approved manual. Without a manual, the guidelines point to the schedules in AS 2550.10, the safe-use standard they cite for these inspections.