Trim cycle lengths in Maryland and Missouri rules and in PG&E's vegetation programs
Maryland's rule sets a 4-year or 5-year trim cycle, Missouri's schedule runs 4 years in urban areas and about 6 in rural areas, and PG&E inspects its distribution lines every year.
Checked against the sources at the bottom of this page on October 15, 2026. Rules, fees and pay change: the source has the last word.
This page reports what the official source says. It is not legal advice: ask the office named here. The state rules are COMAR 20.50.12.09 in Maryland and 20 CSR 4240-23 in Missouri. The PG&E documents are Utility Standard TD-7102S for distribution and Utility Procedure TD-7103S for transmission. The wider rule register is in state vegetation management rules.
Cycles at a glance
| Document | Cycle | Checkpoints |
|---|---|---|
| Maryland, COMAR 20.50.12.09 | 4-year or 5-year trim cycle | 4-year: 15, 40, 70, 100 percent of distribution miles at 12, 24, 36, 48 months |
| Missouri, 20 CSR 4240-23 | Urban 4 years, rural 6 years to first full coverage | 15, 40, 70, 100 percent of urban miles at 12, 24, 36, 48 months |
| PG&E, TD-7102S distribution | Annual Patrol, plus Second Patrol in defined areas | Second Patrol about six months after the Annual Patrol |
| PG&E, TD-7103S transmission | Annual inspection each calendar year | No more than 18 months between inspections |
Maryland
COMAR 20.50.12.09, section F, ties the work to the cycle a utility is on. A utility on a 4-year cycle performs vegetation management on at least 15 percent of its distribution miles within 12 months, 40 percent within 24 months, 70 percent within 36 months and 100 percent within 4 years. On a 5-year cycle the figures are 12, 32, 56, 75 and 100 percent at 12, 24, 36, 48 months and 5 years. Each later cycle follows the same schedule.
Clearances tie to the cycle too. Above 34.5 kV the horizontal clearance is the greater of 15 feet or 4 years' growth on a 4-year cycle, or 5 years' growth on a 5-year cycle. From 14 kV to 34.5 kV the floor is 10 feet. Below 14 kV but at least 600 volts, it is the growth alone.
Missouri
Section (9) of 20 CSR 4240-23 sets separate clocks for urban and rural distribution miles. Urban miles reach 15 percent at 12 months, 40 percent at 24, 70 percent at 36 and 100 percent at the four year anniversary of the rule. Rural miles reach 15 percent at 18 months, 40 percent at 36, 70 percent at 54 and 100 percent at the six year anniversary.
After that, the rule asks for at least 25 percent of urban miles each year and 25 percent of rural miles each 18 months. Minimum clearances at the time of work are 15 feet above 50,000 volts and 10 feet from 600 to 50,000 volts, or the edge of the right of way if that is less, to the extent easements allow. Mature trees strong enough to avoid damaging a conductor are exempt at or below 35,000 volts.
PG&E distribution, TD-7102S
The standard, revision 2, was published April 20, 2023 and took effect June 20, 2023. Annual Patrol inspects all overhead primary and secondary distribution conductors and facilities, excluding service drops. Second Patrol covers the same lines within defined geographic areas.
The Second Patrol is usually planned with a six-month offset from the Annual Patrol, a timing that can vary. Work is done before vegetation breaches compliance. Starting with the 2024 inspection cycle, tree work is completed within one year of identification unless a constraint is documented. Appendix A sets minimum distances for primary conductors above 750 volts: 18 inches in local responsibility areas outside high fire threat districts, and 4 feet in high fire threat districts and, during fire season, in state responsibility areas.
PG&E transmission, TD-7103S
Revision 4, published November 27, 2024 and effective January 27, 2025, has the Annual Patrol inspect all overhead transmission facilities using LiDAR, followed by ground patrols. NERC inspections occur each calendar year with no more than 18 months between them, and NERC tree work is completed by December 31 each year. Where pruning is required, the procedure prescribes multiple years of clearance, and at least one year. Felling is prescribed for vegetation that would need pruning twice a year.
Sources
- Maryland Division of State Documents, COMAR 20.50.12.09, Vegetation Management Requirements, read October 15, 2026
- Missouri Secretary of State, Code of State Regulations, 20 CSR 4240-23, edition dated August 31, 2026, read October 15, 2026
- Pacific Gas and Electric Company, Utility Standard TD-7102S, Distribution Vegetation Management Program, revision 2, read October 15, 2026
- Pacific Gas and Electric Company, Utility Procedure TD-7103S, Vegetation Management Transmission Program, revision 4, read October 15, 2026